Carrier 58HDV Blower Adjustments, Changing Blower Speed, Continuous- Fan using G

Page 44

58HDV

To check temperature rise,use the following procedure:

1.Place thermometers in supply and return air registers as close to furnace as possible, avoiding direct radiant heat from heat exchangers.

2.Operate furnace on High Heat for 10 minutes with all the registers and duct dampers open by using a jumper wire on R to W1 and W2 thermostat connections on the furnace control board.

Note: The SW1 DIP switch #3 should be in the on position. (See furnace wiring diagram)

3.Take readings and compare with range specified on rating plate.

4.If the temperature rise is not in the correct range, the blower speed must be changed. A higher blower speed will lower the temperature rise. A lower blower speed will increase the temperature rise.

5.Repeat steps 2 thru 4 with the furnace operating on Low Heat for 10 minutes by using a jumper wire on the R to W1 thermostat connections on the furnace control board.

6.Remove the jumper wire after the adjustments are complete. Return SW1 DIP switch #3 to previous setting.

Blower Adjustments

Changing Blower Speed

!WARNING

ELECTRICAL SHOCK HAZARD

Failure to follow this warning could result in personal injury or death.

Turn OFF power to furnace before changing blower speed.

NOTE: The blower speeds that the manufacturer sets from the factory for this product are based on a nominal 400 CFM (189 L/s) per ton cooling and the mid range on the temperature rise for heating.

Since the manufacturer cannot predict the static pressure that will be applied to the furnace, it is the responsibility of the installing dealer/contractor to select the proper speeds for the application when the furnace is installed.

If it is necessary to change speeds, refer to steps below.

1.The 115 VAC power supply to the furnace must be turned OFF before making adjustments to the motor.

NOTE: Allow at least 1 minute before restoring power to the furnace after making Blower Control changes.

2.The heating, cooling and continuous blower speeds can be adjusted by changing the SW2 DIP switch settings that are located on the Tap Select Interface Board (See Fig. 54).

SSwitches #1 and #2 adjust the continuous blower speeds. Switches #3 and #4 adjust the heating speed.

Switches #5 and #6 adjust the cooling speed.

Switches #7 and #8 adjust the cooling speed on/off delay profiles. See the “Technical Support Manual” for the switch settings for the desired airflow rates for the installation.

The jumper J1 is used to slightly increase (+) or decrease (-)or not change (NOM) the blower speed selected from SW2. J1 effects BOTH cooling and heating airflow.

SContinuous blower selection DIP 10 and 11 will cause the blower to run in high cooling speed for all low cooling (Y1) calls. Continuous blower DIP settings of 00 and 01 will allow low cooling (Y1) calls to operate normally.

Continuous- Fan using “G”

Energizing the ”G” terminal on the furnace control board provides continuous fan operation. This is done by connecting the G terminal of the thermostat to the G terminal on the furnace control board. When the FAN switch is turned from auto to ON the fan will operate continuously at airflow selected by DIP SW2 switch #1 and DIP SW2 switch #2. EAC will be energized in this mode.

NOTE: In heating, the fan will not turn off during furnace ignition and warm up.

Hard Wired Continuous Fan Operation

Not available for variable speed models.

FURNACE MAINTENANCE

!WARNING

FIRE, EXPLOSION, OR CARBON MONOXIDE HAZARDS

Failure to follow this warning could result in personal injury, death and/or property damage.

It is recommended that the furnace be inspected and serviced on an annual basis (before the heating season) by a qualified service technician.

!WARNING

ELECTRICAL SHOCK, FIRE OR EXPLOSION HAZARD

Failure to follow this warning could result in personal injury, death, and/or property damage.

Before servicing, disconnect all electrical power to furnace.

When servicing controls, label all wires prior to disconnecting. Reconnect wires correctly.

Verify proper operation after servicing.

See “User’s Information Manual” and the “Service Manual”.

44

Image 44
Contents Installation Instructions Required Notice for Massachusetts Installations FIRE, EXPLOSION, and Asphyxiation Hazard Furnace Reliability HazardCUT Hazard Water Damage to Property Hazard Frozen Water Pipe HazardWinter Shutdown Installation Positions Installation RequirementsLocation and Clearances Carbon Monoxide Poisoning HazardFurnace Installation Considerations Horizontal Furnace InstallationCondensate Trap and Drain Lines LevelingDimensions and Clearances Outdoor Combustion Air Method Air Openings and Connecting DuctsKnock Outs Confined Space Installation RequirementsIndoor Combustion Air Unconfined Space Make the Following Check Ventilation AirVenting and Combustion Air Check Contaminated Combustion Air For Two Pipe Installation Direct VentDual Certified Direct or Non- Direct Vent Combustion Air and Vent Piping Insulation Guidelines Sizing Combustion Air and Vent PipeVent Termination Clearances Single Piping onlyDirect Vent Termination Clearance Other than Direct Vent Termination Clearance Condensate Drain Trap Frozen and Burst Water Pipe HazardUpflow Installations Top Vent See Fig OnlyUpflow Installations Vent through Left-Side See Fig Side ViewAll Models Vent through Right-Side See Fig PVCDownflow Left-Side Vent and Trap See Fig ExhaustDownflow Right-Side Vent and Trap See Fig Downflow Right-Side Vent and TrapHorizontal Left through Top See Fig ExhaustHorizontal Left-Side Vent See Fig InletHorizontal Right through Top See Fig Horizontal Right through TopHorizontal Right-Side Vent See Fig ExhaustVent Pipe Connection Connecting Vent and Combustion Air PipingCombustion Air Pipe Connection Direct Vent Horizontal Termination Connecting Vent Pipes and TerminationJoining Pipe and Fittings Using Exterior Risers Vertical TerminationVent Termination Shielding Multi Vent Termination ClearancesConcentric Vent and Combustion-Air Carbon Monoxide POISONING, Fire and Explosion Hazard Concentric Vent TerminationVertical & Horizontal Termination 40,000, 50,000, 60,000, & 75,000 Btuh Furnaces Gas Piping Requirements Gas Supply RequirementsFire and Explosion Hazard Fire HazardElectrical Operation Hazard Typical Gas Piping for UpflowHigh Altitude Air Pressure Switch Propane ConversionGeneral Derating Rules Additional Propane Connection RequirementsChanging Orifices for High Altitude Electrical SHOCK, Fire or Explosion HazardPower Supply Wiring Final Gas Piping CheckJunction Box J- Box Relocation Thermostat HeatingCooling Optional EquipmentFurnace Control Fuse Tap Select Interface BoardInstallation ConnectionsSizing InsulationAddition Of Air Conditioning Filter Installation using Filter RackFilters Combustible Floor Installation Subbase for Combustible FloorGas Supply Pressure Manifold Gas Pressure AdjustmentsStartup Main Burner Flame Check Temperature Rise CheckNatural Gas Input Rating Check Blower Adjustments Continuous- Fan using GHard Wired Continuous Fan Operation Changing Blower SpeedOn = OFF = Continuous Circulating Fan G Request Low Cooling Y1 RequestHigh Cooling Y1 & Y/Y2 or Y/Y2 Request Furnace Control Board Diagnostic Codes See Fig Heating Request with Gas Shut OffWiring Diagram Thermostat Wiring Guide No Connection SINGLE-STAGE Thermostat TWO-STAGE Catalog No 58HDV---01SI