Control module

The GCM control module responds to signals from the room thermostat, air pressure switch, inlet water sensor and boiler limit circuit to operate the circulators, gas valve, igniter and blower. When a room thermostat calls for heat, the GCM starts the system circulator and blower.

The GCM runs the blower long enough to purge the boiler flue passages, then turns on the igniter and lets it warm up.

After a 15-second warmup, the GCM opens the gas valve, turns the igniter off, and checks for flame. The flame must come on within 4 seconds or the GCM will shut down and try the full cycle again.

When the room thermostat is satisfied, the GCM turns off the boiler components and waits for the next heat call.

The GCM indicator lights show normal sequence when the lights are on steady. When a problem occurs, the GCM flashes combinations of lights which indicate the most likely reason for the problem.

Transformer

The control transformer reduces line voltage to 24 volts for the gas valve and limit circuit.

Blower

The blower pulls in air and mixes it with gas from the gas valve. The blower forces this mixture into the burner for combustion inside the boiler chamber.

Air pressure switch

The air pressure switch signals the control module, telling the control module whether air is moving through the blower.

Water temperature limit switch

The water temperature limit switch turns off the gas valve if the temperature in the boiler goes above its setting. (The circulators will continue to run as long as there is a call for heat.)

System circulator

The system circulator circulates water through the external (system) piping. The flow rate of the circulator is controlled by the GCM, depending on the temperature of the water entering the boiler sections.

Bypass circulator

The GCM operates the bypass circulator to mix hot water from the boiler outlet with colder return water from the system as needed to prevent condensation of flue gases in the boiler.

When the water returning to the boiler is below 130 °F, the GCM regulates the bypass circulator and system circulator flow rates to raise the return water temperature up to 130 °F before it enters the boiler sections. By balancing these flow rates, the GCM can protect against condensation even if return water is as low as 60 °F.

Water temperature sensor

The water temperature sensor monitors the temperature of the water entering the boiler sections. The sensor sends this information to the GCM. The GCM determines how much to adjust the circulator flow rates to provide at least 130 °F entering water.

2

Part number 550-141-850/0699

Image 2
Contents Gold GV How it works Gold GV Water boiler Series Hazard definitions Installer User Please read before proceedingBoiler water When servicing boilerBoiler operation Contents Contents Ia Prepare boiler location overview Overview of this sectionInstallations must follow these codes Ib Prepare boiler location codes & altitudeLarge space Ic Prepare boiler location clearancesClearance options Small spaceFlooring and foundation Residential garage installationPrecautions FlooringGV special vent system Id Prepare boiler location vent systemRemoving from existing vent Ie Prepare boiler location contamination Air contaminationIf Prepare boiler location air openings Special considerations GV in small space less than aloneIIa Prepare boiler overview IIb Prepare boiler vent starter tee & drainScrew hole Base rail Insert Cpvc elbow Natural gas Plate installationIIc Prepare boiler orifice plate PropaneBottom side of boiler front section When required IId Prepare boiler high altitude kitAltitudes above 5,500 feet only White Hose RedIIe Prepare boiler place in position Rotate Prepare boiler for test Fig IIf Prepare boiler pressure testPerform hydrostatic pressure test Fill and pressure testPiping connections for hydrostatic test IIIa Water piping overview For heating system with See pages 27 30Install relief valve IIIb Water piping relief valveAir separator IIIc Water piping boiler connectionsSupply & return connections Expansion tankPiping closed IIId Water piping all systems Zoning with circulatorsIIIe Water piping baseboard system Baseboard system pipingIIIf Water piping radiator system Radiator system pipingIIIg Water piping single-zone radiant or heat pump system Multi-zone radiant heating system piping Outdoor reset controlIIIh Water piping multi-zone radiant system IIIi Water piping snow melt system Manual bypass valves for fixed temp operation onlyIIIj Water piping water chiller systems Water chiller systemsIV Venting and combustion air Propane Gas Connecting gas supply piping to boilerGas piping Feet Wiring connections VI Field wiringElectrical installation must comply with ThermostatsField wiring Factory wiring VIIb Start-up preparation Freeze protection when usedVIIa Start-up overview Verify water chemistryCheck for gas leaks VIIb Start-up preparationVerify gas/air orifice plate Fill the system with waterPerform final checks before starting boiler VIIc Start-up read SectionVIId Start-up to operate boiler Start the boilerVIId Start-up operate boiler VIIe Start-up if boiler doesn’t startCheck Gas Control Set Point Connect and adjust manometerVIIf Start-up altitude over 5,500 feet only At Least Inches VIIIa Check-out procedure overview Check-out procedure checklistVIIIb Check-out procedure checklist Shows the ladder wiring diagram for the GV series 3 boiler IXa Operation overviewIXb Operation sequence StepsIXb Operation wiring diagrams Ladder diagram legendGCM For Your Safety Read Before Operating IXc Operation lighting instructionsWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Xb Service and maintenance schedule Service technicianXc Service & maintenance annual start-up Annual start-up only by qualified service technicianStart-up Xc Service & maint. annual start-upcont Annual start-up check/testIgniter Expansion tankGauges Review with owner Annual start-up owner reviewBoiler relief valve Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview Check the following XIb Troubleshooting proceduresBefore troubleshooting XIc Troubleshooting air pressure switch Checking the air pressure switchIgniter XId Troubleshooting servicing tipsBlower Housing Gas ValveXIe Troubleshooting control module Control ModulePower XIf Troubleshooting common problems Symptom Common Causes Possible CorrectionsSymptom Common Causes Possible Corrections XIg Troubleshooting GCM lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview XIIb Replacement parts accessory bag Water trim bag assembly #1XIIc Replacement parts section assembly Description Model Weil-McLain Number Part number85041 XIId Replacement parts jacket assembly 422-200-22885042 XIIe Replacement parts Blower assembly 382-200-340Vent starter tee not included XIIf Replacement parts trim assembly Description Weil-McLain Number Part number85048 XIIg Replacement parts interior panel Interior panel Xiii Dimensions and ratings NumberDOE Gold GV Water boiler Series