Annual start-up only by qualified service technician

The boiler should be inspected and started annually, at the beginning of the heating season, only by a qualified service technician. In addition, the maintenance and care of the boiler designated in Table 4 and explained on the following pages must be performed to assure maximum boiler efficiency and reliability. Failure to service and maintain the boiler and system could result in equipment failure.

Annual start-up — inspect

Reported problems

Inspect any problems reported by owner and correct before proceeding.

Boiler area

1.Verify that boiler area is free of any combustible materials, gasoline and other flammable vapors and liquids.

2.Verify that boiler area (and air intake) is free of any of the contaminants listed on page 13 of this manual. If any of these are present in the boiler intake air vicinity, they must be removed. If they cannot be removed, install combustion air piping to the boiler in accordance with the appropriate venting supplement.

Air openings

1.Verify that combustion and ventilation air openings to the boiler room and/or building are open and unobstructed. Check operation and wiring of automatic combustion air dampers, if used.

2.Verify that boiler vent discharge and air intake are clean and free of obstructions.

Flue gas vent system (and air inlet piping)

1.Visually inspect entire flue gas venting system (and air piping, if installed) for blockage, deterioration or leakage. Repair any joints that show signs of leakage in accordance with vent manufacturer’s instructions. When air is ducted to boiler, verify that air inlet hose is connected and properly sealed.

Failure to inspect for the above conditions and have them repaired can result in severe personal injury or death.

Boiler heating surfaces

1.Obtain a GV gasket replacement kit. This kit contains four gaskets — igniter gasket, vent starter tee gasket, inspection port gasket, and burner gasket.

Electrical shock hazard — Turn off power to the boiler before any service operation on the boiler except as noted otherwise in this instruction manual. Failure to turn off electrical power could result in electrical shock, causing severe personal injury or death.

2.Remove the jacket top panel and jacket front panel after turning off power to the boiler.

3.Remove the two nuts retaining the flueway inspection port cover (page 3, item g). Remove the flueway inspection port cover.

4.Inspect the boiler vent outlet area and heating surfaces by looking through the opening.

5.If the boiler flueways show accumulation of soot, follow Cleaning boiler heating surfaces in this manual section to remove the blower housing and clean the boiler. If there is evidence of a large accumulation of rusty scale deposits, check the temperature mixing system.

6.Replace the flueway inspection port cover.

58

Part number 550-141-850/0699

Image 58
Contents Gold GV How it works Gold GV Water boiler Series Hazard definitions Installer User Please read before proceedingBoiler operation When servicing boilerBoiler water Contents Contents Ia Prepare boiler location overview Overview of this sectionInstallations must follow these codes Ib Prepare boiler location codes & altitudeLarge space Ic Prepare boiler location clearancesClearance options Small spaceFlooring and foundation Residential garage installationPrecautions FlooringRemoving from existing vent Id Prepare boiler location vent systemGV special vent system Ie Prepare boiler location contamination Air contaminationIf Prepare boiler location air openings Special considerations GV in small space less than aloneIIa Prepare boiler overview IIb Prepare boiler vent starter tee & drainScrew hole Base rail Insert Cpvc elbow Natural gas Plate installationIIc Prepare boiler orifice plate PropaneBottom side of boiler front section When required IId Prepare boiler high altitude kitAltitudes above 5,500 feet only White Hose RedIIe Prepare boiler place in position Rotate Prepare boiler for test Fig IIf Prepare boiler pressure testPerform hydrostatic pressure test Fill and pressure testPiping connections for hydrostatic test IIIa Water piping overview For heating system with See pages 27 30Install relief valve IIIb Water piping relief valveAir separator IIIc Water piping boiler connectionsSupply & return connections Expansion tankPiping closed IIId Water piping all systems Zoning with circulatorsIIIe Water piping baseboard system Baseboard system pipingIIIf Water piping radiator system Radiator system pipingIIIg Water piping single-zone radiant or heat pump system IIIh Water piping multi-zone radiant system Outdoor reset controlMulti-zone radiant heating system piping IIIi Water piping snow melt system Manual bypass valves for fixed temp operation onlyIIIj Water piping water chiller systems Water chiller systemsIV Venting and combustion air Gas piping Connecting gas supply piping to boilerPropane Gas Feet Wiring connections VI Field wiringElectrical installation must comply with ThermostatsField wiring Factory wiring VIIb Start-up preparation Freeze protection when usedVIIa Start-up overview Verify water chemistryCheck for gas leaks VIIb Start-up preparationVerify gas/air orifice plate Fill the system with waterPerform final checks before starting boiler VIIc Start-up read SectionVIId Start-up to operate boiler Start the boilerVIId Start-up operate boiler VIIe Start-up if boiler doesn’t startVIIf Start-up altitude over 5,500 feet only Connect and adjust manometerCheck Gas Control Set Point At Least Inches VIIIa Check-out procedure overview Check-out procedure checklistVIIIb Check-out procedure checklist Shows the ladder wiring diagram for the GV series 3 boiler IXa Operation overviewIXb Operation sequence StepsIXb Operation wiring diagrams Ladder diagram legendGCM For Your Safety Read Before Operating IXc Operation lighting instructionsWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Xb Service and maintenance schedule Service technicianXc Service & maintenance annual start-up Annual start-up only by qualified service technicianStart-up Xc Service & maint. annual start-upcont Annual start-up check/testGauges Expansion tankIgniter Boiler relief valve Annual start-up owner reviewReview with owner Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview Before troubleshooting XIb Troubleshooting proceduresCheck the following XIc Troubleshooting air pressure switch Checking the air pressure switchIgniter XId Troubleshooting servicing tipsBlower Housing Gas ValveXIe Troubleshooting control module Control ModulePower XIf Troubleshooting common problems Symptom Common Causes Possible CorrectionsSymptom Common Causes Possible Corrections XIg Troubleshooting GCM lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview XIIb Replacement parts accessory bag Water trim bag assembly #1XIIc Replacement parts section assembly Description Model Weil-McLain Number Part number85041 XIId Replacement parts jacket assembly 422-200-22885042 XIIe Replacement parts Blower assembly 382-200-340Vent starter tee not included XIIf Replacement parts trim assembly Description Weil-McLain Number Part number85048 XIIg Replacement parts interior panel Interior panel Xiii Dimensions and ratings NumberDOE Gold GV Water boiler Series