IXb Operation — sequence

Figure 22 Ignition control module sequence of operation — status light indications

Steps

 

POWER TSTAT

LIMIT

PRESS FLAME

 

Call for

CIRC

 

SWITCH

Timing

 

 

 

 

 

heat?

 

 

 

 

(Following step 8, cycle goes back to step 1.)

 

 

 

 

 

 

 

 

 

 

 

 

1.

Standby

NO

 

 

 

 

· Waiting for call for heat

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.

Call for heat

 

 

 

 

 

 

· Circulator on

YES

 

 

 

· Blower on

3.Limit circuit

·

Limit controls closed

YES

· Block switch contacts closed

 

 

 

 

 

4. Pressure circuit

 

 

·

Pressure switch contacts closed

YES

35 sec

 

 

·Igniter heating

5.Flame proven

·Gas valve open

·

Ignitor remains on

YES

6 sec

 

 

·

Boiler producing heat

 

 

 

 

 

6. Limit cycle

 

 

·

Limit circuit open

YES

· Gas valve closed

7.Flame outage *

· Flame out

YES

· Boiler recycles

8.Thermostat satisfied

· Circulator off

NO

30 sec

·Blower postpurge

or

= "ON"

= "OFF"

*If flame is not proven in 4 seconds, boiler recycles 2 times to retry for ignition before going into lockout. Recycle igniter timing is 30 seconds. Postpurge and prepurge are performed on every cycle. In event of lockout, ignition control will automatically restore sequence of operation after either:

1 hour waiting period.

Opening and closing of thermostat circuit.

Removal of 120 VAC power for at least 45 seconds.

85050

Part number 550-141-850/0699

51

Image 51
Contents Gold GV How it works Gold GV Water boiler Series Please read before proceeding Hazard definitions Installer UserWhen servicing boiler Boiler operationBoiler water Contents Contents Overview of this section Ia Prepare boiler location overviewIb Prepare boiler location codes & altitude Installations must follow these codesSmall space Ic Prepare boiler location clearancesClearance options Large spaceFlooring Residential garage installationPrecautions Flooring and foundationId Prepare boiler location vent system Removing from existing ventGV special vent system Air contamination Ie Prepare boiler location contaminationIf Prepare boiler location air openings GV in small space less than alone Special considerationsIIb Prepare boiler vent starter tee & drain IIa Prepare boiler overviewScrew hole Base rail Insert Cpvc elbow Propane Plate installationIIc Prepare boiler orifice plate Natural gasBottom side of boiler front section IId Prepare boiler high altitude kit When requiredWhite Hose Red Altitudes above 5,500 feet onlyIIe Prepare boiler place in position Rotate Fill and pressure test IIf Prepare boiler pressure testPerform hydrostatic pressure test Prepare boiler for test FigPiping connections for hydrostatic test For heating system with See pages 27 30 IIIa Water piping overviewIIIb Water piping relief valve Install relief valveExpansion tank IIIc Water piping boiler connectionsSupply & return connections Air separatorPiping closed Zoning with circulators IIId Water piping all systemsBaseboard system piping IIIe Water piping baseboard systemRadiator system piping IIIf Water piping radiator systemIIIg Water piping single-zone radiant or heat pump system Outdoor reset control IIIh Water piping multi-zone radiant systemMulti-zone radiant heating system piping Manual bypass valves for fixed temp operation only IIIi Water piping snow melt systemWater chiller systems IIIj Water piping water chiller systemsIV Venting and combustion air Connecting gas supply piping to boiler Gas pipingPropane Gas Feet Thermostats VI Field wiringElectrical installation must comply with Wiring connectionsField wiring Factory wiring Verify water chemistry Freeze protection when usedVIIa Start-up overview VIIb Start-up preparationFill the system with water VIIb Start-up preparationVerify gas/air orifice plate Check for gas leaksStart the boiler VIIc Start-up read SectionVIId Start-up to operate boiler Perform final checks before starting boilerVIIe Start-up if boiler doesn’t start VIId Start-up operate boilerConnect and adjust manometer VIIf Start-up altitude over 5,500 feet onlyCheck Gas Control Set Point At Least Inches Check-out procedure checklist VIIIa Check-out procedure overviewVIIIb Check-out procedure checklist IXa Operation overview Shows the ladder wiring diagram for the GV series 3 boilerSteps IXb Operation sequenceLadder diagram legend IXb Operation wiring diagramsGCM IXc Operation lighting instructions For Your Safety Read Before OperatingWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Service technician Xb Service and maintenance scheduleAnnual start-up only by qualified service technician Xc Service & maintenance annual start-upStart-up Annual start-up check/test Xc Service & maint. annual start-upcontExpansion tank GaugesIgniter Annual start-up owner review Boiler relief valveReview with owner Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview XIb Troubleshooting procedures Before troubleshootingCheck the following Checking the air pressure switch XIc Troubleshooting air pressure switchGas Valve XId Troubleshooting servicing tipsBlower Housing IgniterControl Module XIe Troubleshooting control modulePower Symptom Common Causes Possible Corrections XIf Troubleshooting common problemsSymptom Common Causes Possible Corrections Chart 1 Troubleshooting Power light status XIg Troubleshooting GCM lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview Water trim bag assembly #1 XIIb Replacement parts accessory bagDescription Model Weil-McLain Number Part number XIIc Replacement parts section assembly85041 422-200-228 XIId Replacement parts jacket assembly85042 382-200-340 XIIe Replacement parts Blower assemblyVent starter tee not included Description Weil-McLain Number Part number XIIf Replacement parts trim assembly85048 XIIg Replacement parts interior panel Interior panel Number Xiii Dimensions and ratingsDOE Gold GV Water boiler Series