I. | Prepare boiler location | • Verify code compliance. | 8 – 15 |
|
| Check for high altitude requirements. |
|
|
| Provide required clearances and accessibility. |
|
|
| Plan vent and combustion air provisions. |
|
|
| Check existing common vents to be sure they will work when |
|
|
| old boiler is removed from system. |
|
|
|
|
|
II. | Prepare boiler | Leave boiler on its skid until preparation complete. | 16 – 25 |
|
| Install vent starter tee. |
|
|
| Inspect/replace if necessary the gas/air orifice. |
|
|
| Install high altitude kit (over 5,500 feet). |
|
|
| Place boiler in position. |
|
|
| Hydrostatically test boiler. |
|
|
|
| |
III. Water piping | Select system type from navigation table on page 26, cover- | 26 – 36 | |
|
| ing baseboard systems, radiator systems, radiant heating |
|
|
| systems, heat pump systems, snow melt systems and water |
|
|
| chiller systems. |
|
|
| Review boiler connections pages 28 – 29, including instal- |
|
|
| lation of air separator and expansion tank. |
|
|
| Review general system information, page 30. |
|
|
| Obtain any system components needed but not on hand at |
|
|
| the job site. |
|
|
| Install relief valve and discharge piping. |
|
|
| Connect system piping. |
|
|
| Install low water cutoff and additional limit control, if |
|
|
| required. |
|
|
|
|
|
IV. | Venting and combustion air | Refer to Vent supplements included with boiler | 37 |
|
|
|
|
V. | Gas piping | Connecting gas supply, including need for pipe supports. | 38 – 39 |
|
| Natural gas boilers — gas line sizing (for 0.3" w.c. drop). |
|
|
| Propane boilers — refer to gas supplier. |
|
|
|
|
|
VI. | Field wiring | Code compliances. | 40 – 41 |
|
| Wiring must be N.E.C. Class 1. |
|
|
| Thermostat connections. |
|
|
| Junction box installation. |
|
|
| Field wiring diagram. |
|
|
|
|
|