GOLD GV Water boiler series 3 — manual
VIIIa Check-out procedure — overview
Overview of this section
❏Perform the checklist following to ensure boiler is operating correctly.
❏Fill in the Installation and service certificate at the end of the checklist.
VIIIb
Check off steps as completed
Check-out procedure — checklist
!Boiler and heat distribution units filled with water?
!Automatic air vent, if used, open one full turn?
!Air purged from system?
!Air purged from gas piping? Piping checked for leaks?
!Is proper orifice plate installed? Refer to manual Section IIc to check size and fuel type.
Proper orifice plate must be used. Failure to do so will cause severe personal injury, death or substantial property damage.
!Followed operating instructions on boiler or in manual Section VII for proper
!Is igniter glow visible? Refer to Verify igniter operation, manual Section VIId, step 5.
!Inspect vent system for leaks. Verify vent (and air) piping are functional and unobstructed.
!Test limit control — While burner is operating, move indicator on limit control below actual boiler water temperature. Blower and burner should go off while circulator continues to operate. Raise setting on limit control above boiler water temperature and burner should reignite.
!Test additional
!Test ignition system (control module):
a.Connect voltmeter to gas valve terminals.
b.Turn off manual gas valve.
c.Set thermostat to call for heat.
d.Control module will begin purge cycle, then activate igniter. Igniter will glow for approximately 20 seconds. Near end of 20 seconds, 24 VAC will show at gas valve for approximately 6 seconds and then
48 | Part number |