Weil-McLain GOLD DV WATER BOILER manual IIIc Water piping boiler connections, Air separator

Page 28

GOLD GV Water boiler series 3 — manual

IIIc Water piping — boiler connections

Supply & return connections

Always connect supply and return connections to the boiler as shown in Figure 9. (Note in the following and in the suggested piping drawings in this manual that the expansion tank and air separator location will depend on the system piping.)

Operating pressure of system, after temperature expansion above cold fill pressure, should not exceed 24 PSIG to avoid weeping of relief valve.

Install an automatic air vent on top of the air separator, per separator manufacturer’s instructions.

Closed-type expansion tank:

Air separator

Install an air separator in the piping as shown. For single-zone systems, install the air separator in the return piping as shown in Figure 9. This allows mounting the automatic air vent and expansion tank off of the separator.

Expansion tank

Figures 9 and 10 show typical installation of the expansion tank when the boiler is connected to a zone- valve zoned baseboard system (see Figure 10). Always locate the air separator and expansion tank as shown in the suggested piping drawings, Figures 10 through 16.

Ensure that the expansion tank size will handle boiler and system water volume and temperature. See tank manufacturer’s instructions and ratings for details. Additional tanks may be added to the system if needed to handle the expansion. These tanks may be installed by connecting to tees in the system piping.

Undersized expansion tanks

cause system water to be lost from the relief valve and makeup water to be added through the fill valve. Eventual section failure can result.

Always locate the cold water fill connection at the expansion tank. Never locate this elsewhere in the system.

Diaphragm- or bladder-type tank:

Refer to Figure 9 for suggested piping when using a diaphragm- or bladder-type expansion tank.

Diaphragm- or bladder-type expansion tank — Control fill pressure with the tank air charge pressure. Always check pressure and charge tank with tank removed from system to be sure reading is accurate. Boiler relief valve is set for 30 PSIG.

Figure 10 shows suggested piping when using a closed- type expansion tank, in which the air is directly in contact with tank water.

Connect piping (½" or ¾") from the air separator top outlet to the tank fitting. Slope any horizontal piping a minimum of 1 inch per 5 feet of horizontal pipe.

Always use a tank fitting, such as the B&G Tanktrol or Taco Taco-Trol(shown). The fitting reduces gravity flow of water in the piping to the tank, avoids air bubbling through the tank water, and provides the proper fill height in the tank.

Correct all leaks in the system or tank piping. Leaks allow air to escape from the system and will cause water- logging of the tank. This will result in water loss through the boiler relief valve due to over-pressurization.

NEVER use an automatic air vent in a system equipped with a closed-type expansion tank. The air removed from the system will cause water- logging of the expansion tank.

Closed-type expansion tank — Follow tank manufacturer’s instructions for filling the tank. Typical tank sizing provides for approximately 12 PSIG when the tank is filled to the normal level and system water is cold. Note that boiler relief valve is set for 30 PSIG. Operating pressure of system, after temperature expansion above cold fill pressure, should not exceed 24 PSIG to avoid weeping of relief valve.

Backflow preventer

Where required by codes, install a backflow preventer in the cold water fill line, as shown in suggested piping diagrams on following pages. Install a check valve if a backflow preventer is not installed.

28

Part number 550-141-850/0699

Image 28
Contents Gold GV How it works Gold GV Water boiler Series Hazard definitions Installer User Please read before proceedingBoiler operation When servicing boilerBoiler water Contents Contents Ia Prepare boiler location overview Overview of this sectionInstallations must follow these codes Ib Prepare boiler location codes & altitudeIc Prepare boiler location clearances Clearance optionsLarge space Small spaceResidential garage installation PrecautionsFlooring and foundation FlooringRemoving from existing vent Id Prepare boiler location vent systemGV special vent system Ie Prepare boiler location contamination Air contaminationIf Prepare boiler location air openings Special considerations GV in small space less than aloneIIa Prepare boiler overview IIb Prepare boiler vent starter tee & drainScrew hole Base rail Insert Cpvc elbow Plate installation IIc Prepare boiler orifice plateNatural gas PropaneBottom side of boiler front section When required IId Prepare boiler high altitude kitAltitudes above 5,500 feet only White Hose RedIIe Prepare boiler place in position Rotate IIf Prepare boiler pressure test Perform hydrostatic pressure testPrepare boiler for test Fig Fill and pressure testPiping connections for hydrostatic test IIIa Water piping overview For heating system with See pages 27 30Install relief valve IIIb Water piping relief valveIIIc Water piping boiler connections Supply & return connectionsAir separator Expansion tankPiping closed IIId Water piping all systems Zoning with circulatorsIIIe Water piping baseboard system Baseboard system pipingIIIf Water piping radiator system Radiator system pipingIIIg Water piping single-zone radiant or heat pump system IIIh Water piping multi-zone radiant system Outdoor reset controlMulti-zone radiant heating system piping IIIi Water piping snow melt system Manual bypass valves for fixed temp operation onlyIIIj Water piping water chiller systems Water chiller systemsIV Venting and combustion air Gas piping Connecting gas supply piping to boilerPropane Gas Feet VI Field wiring Electrical installation must comply withWiring connections ThermostatsField wiring Factory wiring Freeze protection when used VIIa Start-up overviewVIIb Start-up preparation Verify water chemistryVIIb Start-up preparation Verify gas/air orifice plateCheck for gas leaks Fill the system with waterVIIc Start-up read Section VIId Start-up to operate boilerPerform final checks before starting boiler Start the boilerVIId Start-up operate boiler VIIe Start-up if boiler doesn’t startVIIf Start-up altitude over 5,500 feet only Connect and adjust manometerCheck Gas Control Set Point At Least Inches VIIIa Check-out procedure overview Check-out procedure checklistVIIIb Check-out procedure checklist Shows the ladder wiring diagram for the GV series 3 boiler IXa Operation overviewIXb Operation sequence StepsIXb Operation wiring diagrams Ladder diagram legendGCM For Your Safety Read Before Operating IXc Operation lighting instructionsWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Xb Service and maintenance schedule Service technicianXc Service & maintenance annual start-up Annual start-up only by qualified service technicianStart-up Xc Service & maint. annual start-upcont Annual start-up check/testGauges Expansion tankIgniter Boiler relief valve Annual start-up owner reviewReview with owner Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview Before troubleshooting XIb Troubleshooting proceduresCheck the following XIc Troubleshooting air pressure switch Checking the air pressure switchXId Troubleshooting servicing tips Blower HousingIgniter Gas ValveXIe Troubleshooting control module Control ModulePower XIf Troubleshooting common problems Symptom Common Causes Possible CorrectionsSymptom Common Causes Possible Corrections XIg Troubleshooting GCM lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview XIIb Replacement parts accessory bag Water trim bag assembly #1XIIc Replacement parts section assembly Description Model Weil-McLain Number Part number85041 XIId Replacement parts jacket assembly 422-200-22885042 XIIe Replacement parts Blower assembly 382-200-340Vent starter tee not included XIIf Replacement parts trim assembly Description Weil-McLain Number Part number85048 XIIg Replacement parts interior panel Interior panel Xiii Dimensions and ratings NumberDOE Gold GV Water boiler Series