Weil-McLain GOLD DV WATER BOILER manual IIId Water piping all systems, Zoning with circulators

Page 30

GOLD GV Water boiler series 3 — manual

IIId Water piping — all systems

Zoning with circulators

The GV internal system circulator cannot be removed from the boiler for use as one of the zone circulators. It must remain as shipped from the factory to allow proper flow control inside the boiler. You will need a circulator for each zone.

Size the common (primary) pipe for the combined flow of all circulators, or with a pipe cross-sectional area at least equal to the total areas of all zone supply pipes. You may also use the alternative sizing chart at right, based on maximum flow of 10 gmp per circulator.

Install and wire a separate relay for each zone circulator.

Alternate primary

manifold sizing

(max 10 gpm per circulator)

Number of

Suggested

circulators

pipe size

 

 

 

 

1

1"

 

 

 

2

– 3

1½ "

4

– 5

2"

 

 

 

6

– 8

2½ "

9 – 12

3"

 

 

 

Zoning with zone valves

Each zone in the piping diagrams in this section is shown with an isolation valve on each side. Substitute a memory-stop valve for one of these in each zone in order to use the memory-stop valve for balancing flow as well as isolation.

Provide a separate 24-volt transformer to power the zone valves. Size the transformer to handle the total rated load of all connected zone valves.

Additional components

If installation is to comply with ASME or Canadian requirements, an additional high temperature limit is needed.

Purchase and install in system supply piping between boiler and isolation valve.

Wire the second limit control in series with the boiler limit control.

Set the second limit control at least 20 °F above the boiler limit control setting (maximum setting 240 °F).

A low water cutoff device is required when boiler is installed above radiation level or by certain state or local codes or insurance companies. Use low water cutoff designed for water installations. Electrode probe-type is recommended. Purchase and install in tee in supply piping above boiler.

If boiler is connected to heating coils located in air handling units where they can be exposed to refrigerated air, use flow control valves or other automatic means to prevent gravity circulation during cooling cycle. Circulation of cold water through the boiler could result in damage to the heat exchanger, causing possible severe personal injury, death or substantial property damage.

Do not remove either of the GV internal pumps for use elsewhere in the system. Both pumps are required for proper operation. Removing a pump will cause the boiler to malfunction. Substantial property damage could result.

Never install another pump in series with the GV boiler. Forced flow can cause improper operation of the boiler controls. Substantial property damage could result.

30

Part number 550-141-850/0699

Image 30
Contents Gold GV How it works Gold GV Water boiler Series Hazard definitions Installer User Please read before proceedingWhen servicing boiler Boiler operationBoiler water Contents Contents Ia Prepare boiler location overview Overview of this sectionInstallations must follow these codes Ib Prepare boiler location codes & altitudeLarge space Ic Prepare boiler location clearancesClearance options Small spaceFlooring and foundation Residential garage installationPrecautions FlooringId Prepare boiler location vent system Removing from existing ventGV special vent system Ie Prepare boiler location contamination Air contaminationIf Prepare boiler location air openings Special considerations GV in small space less than aloneIIa Prepare boiler overview IIb Prepare boiler vent starter tee & drainScrew hole Base rail Insert Cpvc elbow Natural gas Plate installationIIc Prepare boiler orifice plate PropaneBottom side of boiler front section When required IId Prepare boiler high altitude kitAltitudes above 5,500 feet only White Hose RedIIe Prepare boiler place in position Rotate Prepare boiler for test Fig IIf Prepare boiler pressure testPerform hydrostatic pressure test Fill and pressure testPiping connections for hydrostatic test IIIa Water piping overview For heating system with See pages 27 30Install relief valve IIIb Water piping relief valveAir separator IIIc Water piping boiler connectionsSupply & return connections Expansion tankPiping closed IIId Water piping all systems Zoning with circulatorsIIIe Water piping baseboard system Baseboard system pipingIIIf Water piping radiator system Radiator system pipingIIIg Water piping single-zone radiant or heat pump system Outdoor reset control IIIh Water piping multi-zone radiant systemMulti-zone radiant heating system piping IIIi Water piping snow melt system Manual bypass valves for fixed temp operation onlyIIIj Water piping water chiller systems Water chiller systemsIV Venting and combustion air Connecting gas supply piping to boiler Gas pipingPropane Gas Feet Wiring connections VI Field wiringElectrical installation must comply with ThermostatsField wiring Factory wiring VIIb Start-up preparation Freeze protection when usedVIIa Start-up overview Verify water chemistryCheck for gas leaks VIIb Start-up preparationVerify gas/air orifice plate Fill the system with waterPerform final checks before starting boiler VIIc Start-up read SectionVIId Start-up to operate boiler Start the boilerVIId Start-up operate boiler VIIe Start-up if boiler doesn’t startConnect and adjust manometer VIIf Start-up altitude over 5,500 feet onlyCheck Gas Control Set Point At Least Inches VIIIa Check-out procedure overview Check-out procedure checklistVIIIb Check-out procedure checklist Shows the ladder wiring diagram for the GV series 3 boiler IXa Operation overviewIXb Operation sequence StepsIXb Operation wiring diagrams Ladder diagram legendGCM For Your Safety Read Before Operating IXc Operation lighting instructionsWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Xb Service and maintenance schedule Service technicianXc Service & maintenance annual start-up Annual start-up only by qualified service technicianStart-up Xc Service & maint. annual start-upcont Annual start-up check/testExpansion tank GaugesIgniter Annual start-up owner review Boiler relief valveReview with owner Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview XIb Troubleshooting procedures Before troubleshootingCheck the following XIc Troubleshooting air pressure switch Checking the air pressure switchIgniter XId Troubleshooting servicing tipsBlower Housing Gas ValveXIe Troubleshooting control module Control ModulePower XIf Troubleshooting common problems Symptom Common Causes Possible CorrectionsSymptom Common Causes Possible Corrections XIg Troubleshooting GCM lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview XIIb Replacement parts accessory bag Water trim bag assembly #1XIIc Replacement parts section assembly Description Model Weil-McLain Number Part number85041 XIId Replacement parts jacket assembly 422-200-22885042 XIIe Replacement parts Blower assembly 382-200-340Vent starter tee not included XIIf Replacement parts trim assembly Description Weil-McLain Number Part number85048 XIIg Replacement parts interior panel Interior panel Xiii Dimensions and ratings NumberDOE Gold GV Water boiler Series