Weil-McLain 550-141-850/0599, GOLD DV WATER BOILER manual Start-up

Page 59

Installation • Start-Up • Parts • Maintenance

Annual start-up — inspect

Water piping

1.Check the boiler interior piping and all system piping for signs of leaks.

2.Repair any leaks before proceeding.

Eliminate all system leaks. Continual fresh makeup water will reduce boiler life. Minerals can build up in sections, reducing heat transfer, overheating cast iron, and causing section failure.

Do not use petroleum-based cleaning or sealing compounds in boiler system. Severe damage to boiler will occur, resulting in substantial property damage.

Condensate drain system

1.Inspect the condensate trap hose for deterioration.

2.Check for any obstructions in the trap hose by squeezing the tubing.

3.If there is any doubt the condensate drain system is flowing freely, remove the clamp and hose from the bottom of the vent starter tee. Slide a funnel outlet into the trap hose and pour water through. It should exit at the termination of the condensate drain line.

4.If the owner’s monthly inspection of the condensate drain system has indicated a tendency for the trap to run dry, install a condensate drain line check valve kit, available through your Weil-McLain distributor. See installation instructions for check valve kit in this manual section.

Annual start-up — service

Blower motor (Figure 27)

1.With boiler power OFF, place a few drops of S.A.E. 20 motor oil in each of the two oil cups.

Use only S.A.E. 20 motor oil to lubricate the blower motor. Do not use universal household oils. Motor could be damaged, resulting in possible severe property damage.

Oiled-bearing circulators

1.Both of the circulators installed in the boiler are water- lubricated. No oiling is required.

2.Check other circulators in the system. Oil any circulators requiring oil, following circulator manufacturer’s instructions. Over-oiling will damage the circulator.

Figure 27 Blower motor

Oil cup

Oil cup

85037

Annual start-up

Start-up procedure

start-up

1. Follow the instructions in manual Section VII.

2.Verify cold fill pressure is correct and that fill system is working properly.

3.Verify antifreeze level (if used) is at the right concentration and that inhibitor level is correct.

4.Check gas piping, per manual Sections V and VIb, verifying no indications of leakage and all piping and connections are in good condition.

5.Read the Lighting instructions (Figure 25 or 26 of this manual or on boiler label) applying to the boiler (ensuring the instruction applies to the gas valve installed in the boiler).

6.Start the boiler following the Lighting instructions and manual Section VIId.

Part number 550-141-850/0699

59

Image 59
Contents Gold GV How it works Gold GV Water boiler Series Please read before proceeding Hazard definitions Installer UserBoiler water When servicing boilerBoiler operation Contents Contents Overview of this section Ia Prepare boiler location overviewIb Prepare boiler location codes & altitude Installations must follow these codesSmall space Ic Prepare boiler location clearancesClearance options Large spaceFlooring Residential garage installationPrecautions Flooring and foundationGV special vent system Id Prepare boiler location vent systemRemoving from existing vent Air contamination Ie Prepare boiler location contaminationIf Prepare boiler location air openings GV in small space less than alone Special considerationsIIb Prepare boiler vent starter tee & drain IIa Prepare boiler overviewScrew hole Base rail Insert Cpvc elbow Propane Plate installationIIc Prepare boiler orifice plate Natural gasBottom side of boiler front section IId Prepare boiler high altitude kit When requiredWhite Hose Red Altitudes above 5,500 feet onlyIIe Prepare boiler place in position Rotate Fill and pressure test IIf Prepare boiler pressure testPerform hydrostatic pressure test Prepare boiler for test FigPiping connections for hydrostatic test For heating system with See pages 27 30 IIIa Water piping overviewIIIb Water piping relief valve Install relief valveExpansion tank IIIc Water piping boiler connectionsSupply & return connections Air separatorPiping closed Zoning with circulators IIId Water piping all systemsBaseboard system piping IIIe Water piping baseboard systemRadiator system piping IIIf Water piping radiator systemIIIg Water piping single-zone radiant or heat pump system Multi-zone radiant heating system piping Outdoor reset controlIIIh Water piping multi-zone radiant system Manual bypass valves for fixed temp operation only IIIi Water piping snow melt systemWater chiller systems IIIj Water piping water chiller systemsIV Venting and combustion air Propane Gas Connecting gas supply piping to boilerGas piping Feet Thermostats VI Field wiringElectrical installation must comply with Wiring connectionsField wiring Factory wiring Verify water chemistry Freeze protection when usedVIIa Start-up overview VIIb Start-up preparationFill the system with water VIIb Start-up preparationVerify gas/air orifice plate Check for gas leaksStart the boiler VIIc Start-up read SectionVIId Start-up to operate boiler Perform final checks before starting boilerVIIe Start-up if boiler doesn’t start VIId Start-up operate boilerCheck Gas Control Set Point Connect and adjust manometerVIIf Start-up altitude over 5,500 feet only At Least Inches Check-out procedure checklist VIIIa Check-out procedure overviewVIIIb Check-out procedure checklist IXa Operation overview Shows the ladder wiring diagram for the GV series 3 boilerSteps IXb Operation sequenceLadder diagram legend IXb Operation wiring diagramsGCM IXc Operation lighting instructions For Your Safety Read Before OperatingWhite-Rodgers gas valve model 36E Xa Service and maintenance overview Service technician Xb Service and maintenance scheduleAnnual start-up only by qualified service technician Xc Service & maintenance annual start-upStart-up Annual start-up check/test Xc Service & maint. annual start-upcontIgniter Expansion tankGauges Review with owner Annual start-up owner reviewBoiler relief valve Condensate drain line Check valve assembly To remove the blower assembly Igniter XIa Troubleshooting overview Check the following XIb Troubleshooting proceduresBefore troubleshooting Checking the air pressure switch XIc Troubleshooting air pressure switchGas Valve XId Troubleshooting servicing tipsBlower Housing IgniterControl Module XIe Troubleshooting control modulePower Symptom Common Causes Possible Corrections XIf Troubleshooting common problemsSymptom Common Causes Possible Corrections Chart 1 Troubleshooting Power light status XIg Troubleshooting GCM lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Limit & Power lights flashing Chart 4 Pres Switch & Power lights flashing Chart 5 Flame & Power lights flashing Chart 6 Tstat Circ light flashing and Power light on steady Chart 7 Limit light flashing and Power light on steady Is thermostat circuit closed continuity across wires? XIIa Replacement parts overview Water trim bag assembly #1 XIIb Replacement parts accessory bagDescription Model Weil-McLain Number Part number XIIc Replacement parts section assembly85041 422-200-228 XIId Replacement parts jacket assembly85042 382-200-340 XIIe Replacement parts Blower assemblyVent starter tee not included Description Weil-McLain Number Part number XIIf Replacement parts trim assembly85048 XIIg Replacement parts interior panel Interior panel Number Xiii Dimensions and ratingsDOE Gold GV Water boiler Series