Installation
Important
Outside the cubicles, group the cables between the MISI boards and those between the APOZ boards with the other auxiliary
links between cubicles and separate all these cables from the power cables.
|
|
| MISI |
|
|
| board |
|
| XM12 | UPS 1 |
| XM7 | XM11 |
|
|
|
| |
| XM6 | XM10 |
|
|
|
| |
A | XM5 |
|
|
|
|
| MISI |
|
|
| board |
|
| XM12 | UPS 2 |
|
|
| |
| XM7 | XM11 |
|
|
|
| |
| XM6 | XM10 |
|
|
|
| |
| XM5 |
|
|
|
|
| MISI |
|
|
| board |
|
| XM12 | UPS 3 |
|
|
| |
| XM7 | XM11 |
|
|
|
| |
| XM6 | XM10 |
|
|
|
| |
| XM5 |
|
|
|
|
| MISI |
|
|
| board |
|
| XM12 | UPS 4 |
| XM7 | XM11 |
|
|
|
| |
| XM6 | XM10 |
|
|
|
| |
| XM5 |
|
|
Fig. 21
2.10Connections between
–make connections with 1 mm2 wires (recommended size, not supplied);
–connect terminals 1 and 2 on connector XM8 on the MISI board in the UPS to terminals 1 and 2 in the external maintenance bypass.
maintenance bypass cubicle
Q3BP | Q5N |
12
| Q3BP + 1 |
|
|
|
|
|
| XM8 |
| ||
MISI 1 | Q3BP - 2 |
|
| ||
|
|
|
| ||
|
|
|
|
| |
| Q3BP + 1 |
| |||
|
| XM8 |
| ||
MISI 2 | Q3BP - 2 |
|
|
|
|
|
|
|
| ||
|
|
|
|
| |
|
|
| MISI 3 | ||
|
|
| MISI 4 |