Appendix G Site Planning and Maintenance Records

Site Preparation Checklist

Se n d d o c u m e n t a t i o n c o m m e n t s t o n ex u s 5 k d o c s @ c i s c o . c o m .

Table G-1

 

Site Planning Checklist

 

 

 

 

 

 

 

 

Task No.

Planning Activity

Verified By

Time

Date

 

 

 

 

 

1

Space evaluation:

 

 

 

 

•

Space and layout

 

 

 

 

•

Floor covering

 

 

 

 

•

Impact and vibration

 

 

 

 

•

Lighting

 

 

 

 

•

Maintenance access

 

 

 

 

 

 

 

 

2

Environmental evaluation:

 

 

 

 

•

Ambient temperature

 

 

 

 

•

Humidity

 

 

 

 

•

Altitude

 

 

 

 

•

Atmospheric contamination

 

 

 

 

•

Air flow

 

 

 

 

 

 

 

 

3

Power evaluation:

 

 

 

 

•

Input power type

 

 

 

 

•

Power receptacles1

 

 

 

 

• Receptacle proximity to the

 

 

 

 

 

equipment

 

 

 

 

• Dedicated circuit for power supply

 

 

 

 

• Dedicated (separate) circuits for

 

 

 

 

 

redundant power supplies

 

 

 

 

• UPS2 for power failures

 

 

 

4

Grounding evaluation:

 

 

 

 

•

Circuit breaker size

 

 

 

 

• CO ground (AC- powered systems)

 

 

 

 

 

 

 

 

5

Cable and interface equipment

 

 

 

 

evaluation:

 

 

 

 

•

Cable type

 

 

 

 

•

Connector type

 

 

 

 

•

Cable distance limitations

 

 

 

 

•

Interface equipment (transceivers)

 

 

 

 

 

 

 

 

6

EMI3 evaluation:

 

 

 

 

• Distance limitations for signaling

 

 

 

 

•

Site wiring

 

 

 

 

•

RFI4 levels

 

 

 

1.Verify that the power supply installed in the chassis has a dedicated AC source circuit.

2.UPS = uninterruptible power supply.

Cisco Nexus 5000 Series Hardware Installation Guide

 

G-2

OL-15902-02

 

 

 

Page 162
Image 162
Cisco Systems 5000 manual Task No Planning Activity Verified By Time Date