Appendix D Site Planning and Maintenance Records

Site Preparation Checklist

Table D-1

 

Site Planning Checklist

 

 

 

 

 

 

 

 

Task No.

Planning Activity

Verified By

Time

Date

 

 

 

 

 

1

Space evaluation:

 

 

 

 

Space and layout

 

 

 

 

Floor covering

 

 

 

 

Impact and vibration

 

 

 

 

Lighting

 

 

 

 

Maintenance access

 

 

 

 

 

 

 

 

2

Environmental evaluation:

 

 

 

 

Ambient temperature

 

 

 

 

Humidity

 

 

 

 

Altitude

 

 

 

 

Atmospheric contamination

 

 

 

 

Air flow

 

 

 

 

 

 

 

 

3

Power evaluation:

 

 

 

 

Input power type

 

 

 

 

Power receptacles1

 

 

 

 

Receptacle proximity to the equipment

 

 

 

 

Dedicated circuit for power supply

 

 

 

 

Dedicated (separate) circuits for redundant

 

 

 

 

 

power supplies

 

 

 

 

UPS2 for power failures

 

 

 

4

Grounding evaluation:

 

 

 

 

Circuit breaker size

 

 

 

 

CO ground (AC- powered systems)

 

 

 

 

 

 

 

 

5

Cable and interface equipment evaluation:

 

 

 

 

Cable type

 

 

 

 

Connector type

 

 

 

 

Cable distance limitations

 

 

 

 

Interface equipment (transceivers)

 

 

 

 

 

 

 

 

6

Electromagnetic interference (EMI) evaluation:

 

 

 

 

Distance limitations for signaling

 

 

 

 

Site wiring

 

 

 

 

RFI3 levels

 

 

 

1.Verify that the power supply installed in the chassis has a dedicated AC source circuit.

2.UPS = uninterruptible power supply.

3.RFI = radio frequency interference.

Cisco MDS 9100 Series Hardware Installation Guide

 

D-2

OL-16187-01

 

 

 

Page 102
Image 102
Cisco Systems MDS 9100 Series manual Task No Planning Activity Verified By Time Date