MODEL 54e pH/ORP

SECTION 6.0

 

THEORY OF OPERATION

6.9PID CONTROL (continued)

5.The reaction of the system, when graphed, will resemble Figure 6-2, showing a change in the measured variable over the change in time. After a period of time (the process delay time), the meas- ured variable will start to increase (or decrease) rapidly. At some further time the process will begin to change less rapidly as the process begins to sta- bilize from the imposed step change. It is important to collect data for a long enough period of time to see the process begin to level off to establish a tan- gent to the process reaction curve.

6.When sufficient data has been collected, return the output signal to its original value using the simulate test function. Maintain the controller in this manual mode until you are ready to initiate automatic PID control, after you have calculated the tuning con- stants.

Once these steps are completed, the resulting process reaction curve is used to obtain information about the overall dynamics of the system. It will be used to cal- culate the needed tuning parameters of the Model 54e pH/ORP controller.

NOTE

The tuning procedure outlined below is adapted from "Instrumentation and Process Measurement and Control", by Norman A. Anderson, Chilton Co., Radnor, Pennsylvania, ©1980.

Information derived from the process reaction curve will be used with the following empirical formulas to predict the optimum settings for proportional and inte- gral tuning parameters.

Four quantities are determined from the process reac- tion curve for use in the formulas: time delay (D), time period (L), a ratio of these two (R), and plant gain (C).

A line is drawn on the process reaction curve tangent to the curve at point of maximum rise (slope) as shown in Figure 6-2. The Time Delay (D), or lag time, extends from "zero time" on the horizontal axis to the point where the tangent line intersects the time axis. The Response Time period (L), extends from the end of delay period to the time at which the tangent line inter- sects the 100% reaction completion line representing the process stabilization value. The ratio (R) of the Response Time period to the Time Delay describes the dynamic behavior of the system.

In the example, the process Delay Time (D) was four seconds and the Response Time period (L) was 12 seconds, so:

R = L 12 seconds = 3

D4 seconds

The last parameter used in the equations is a plant gain

(C). The plant gain is defined as a percent change in the controlled variable divided by the percent change in manipulated variable; in other words, the change in the measured variable (pH, conductivity, temperature) divid- ed by the percent change in the analog output signal.

The percent change in the controlled variable is defined as the change in the measured variable (pH, conductivity, temperature) compared to the measure- ment range, the difference between the 20 mA (Hi) and 4 (or 0) mA (Lo) setpoints, which you determined when configuring the analog output.

In the example shown in Figure 6-2:

The percent change in pH was:

pH2 - pH1

x 100% =

8.2

- 7.2 pH

= 33.3%

 

 

 

 

pH “Hi” - pH “Lo”

9.0

- 6.0 pH

 

The change in the output signal was:

6 - 4 milliamps x 100% = 12.5%

20 - 4

So the Plant Gain is:

C = 33.3 = 2.66 12.5

Once R and C are calculated, the proportional and inte- gral bands can be determined as follows:

Proportional band (%) = P = 286 CR

Integral Time (seconds per repeat) = I = 3.33 D x C

So for the example:

P = 286 (2.66) = 254% 3

I = 3.33 (4 sec.) 2.66 = 36 seconds

To enter these parameters, use the procedure detailed in Section 5.6.

53

Page 59
Image 59
Emerson 54e pH/ORP instruction manual PID Control