User Manual MON20/20 Software for Gas Chromatographs
3-9000-745 SEPTEMBER 2010
4-74
5. If you want the GC to halt after the current analysis when an alarm is
triggered, do the following:
(a.) Select the Halt on Alarm? checkbox.
(b.) Enter a value in the Delay column for the length of time, in
seconds, that the alarm condition should exist before the Halt
command is executed. You can enter a value between 0 and 1800.
6. To save the changes without closing the window, click Save. To save
the changes and close the window, click OK.
4.10 Managing streams
This function allows you to do the following:
Assign component data tables, validation data tables, and timed
events tables to a particular stream.
Designate a stream for analysis, validation, or calibration.
Control automatic calibration or validation parameters, such as the
total number of runs, runs to be averaged, starting times, and time
between automatic calibrations and baseline runs.
Define baseline pressure and temperature conditions that are
applicable to calculated GC analysis data, such as compressibility.

4.10.1 Designating how a stream will be used

To assign how a stream will be used, do the following:
1. Select Streams... from the Application menu. The Streams window
opens.