The following are descriptions of error message s.
Error Message Description/Procedure
Cell Test invoked in
simulator mode.
The simulator mode variable Simulate mode act is
TRUE. The Fiber-Optic Test cannot be run in simulator
mode. Change the simulator mode by setting request
parameter Simulate mode to FALSE and run the Fiber-
Optic Test again.
Cell Test did not run to
completion. Cell Test
request was removed.
The Cell Test command was removed during Cell Test.
The user ma y have abort ed the test.
Cell Test did not run to
completion. Internal Cell
Test fault detected.
A drive trip fault occurred d uring the Fiber-O ptic Test.
Correct and clear any existing trip faults and run the
Fiber-Optic Test again.
Fiber-Optic Test
interrupted.
The Fiber-Optic Test could not be run due to one of the
following reasons:
Voltage was detected on the DC bus.
The static c harger was not in an idle state.
A drive trip fault was detected.
Correct and cl ear any existin g drive trip fault s. Press the
“SWITCHGEAR OPEN” button on the drive cabinet door.
Wait for the dc bus voltage to completely discharge. Run
the Fiber-Optic Test again.
Fiber-Optic Test did not
run. Fiber-Optic Test
cannot be run with
switchgear closed.
Press the “SW ITCHGEAR OPEN” b utton on the driv e.
Wait for the DC bus voltage to completely discharge.