42Chapter 4 Power supply installation
Bringing power and ground into the PDU
Introduction
Install BAT/BATRTN wires in pairs. Each pair of wires supplies voltages to a module through a power harness. The module harnesses are installed in the cabinet PDU and connected to the modules at the factory. See "About the power distribution unit" (page 40).
To bring DC power and ground into the PDU
Step
1If you are using a conduit, terminate the 32 mm
2Select a power feed with a circuit breaker dedicated to each module, and identify it with an appropriate tag.
3Select a wire size to suit the required feed length from the power source (see "DC wire gauge tables" (page 36)).
4Use pliers to strip 6 mm (1/4 in.) to 13 mm (1/2 in.) of the insulation from one end of all power and ground feed wires.
5Undo the terminal block screws at
6Insert the red wires into terminal block positions 0, 1, 2, and 3.
7Secure the wires in the terminal block by tightening the screws.
8Undo the terminal block screws at (+) positions 0, 1, 2, and 3.
9Insert the black wires into terminal block positions 0, 1, 2, and 3.
10Secure the wires in the terminal block by tightening the screws.
11Select a #10 AWG green wire safety ground and attach it to the cabinet.
12Measure the module ground continuity by touching one multimeter lead to any BATRTN terminal block connector and the other end to the GND terminal block connector. Ensure the measurement is between
—End—