Industry Sector, IA&DT

Testing “Tank 1” in Runtime

Load the project to the panel and test the functions in the "Tank 1" screen.

Note

If the reservoir is filled, the drain valve cannot be opened.

You first have to drain the reservoir using the “MANUAL_DRAIN_RES” (I1.6).

If you set the acquisition cycle of all tags to 100 ms, the actuation of the buttons and the valve function will be updated faster.

SCE Training Curriculum

Page 75 of 118

To be used only at Educational and R&D Facilities

TIA Portal Module 090-010, Edition 03/2013

 

Unrestricted / © Siemens AG 2013. All Rights Reserved

SCE_EN_090-010_R1209_ WinCC Advanced with Runtime and TP700 Comfort Panel