Wiring the S7-400
4-38 AutomationSystem S7-400 Hardwareand Installation
A5E00850741-01
4.22 Cable routing in cable ducts or fan subassemblies

Cable Routing

Depending on the number of cables and plug-in lines merging at the particular
rack, the cross-section of the cable duct or fan subassembly may not be sufficient
to accept all cables.
Youshould therefore route half the cables toward each side via the cable duct or
fan subassembly.

Securing Cables

There are eyes for securing cables on both sides of the cable duct or fan
subassembly (see Reference Manual Module Specifications, Chapter 6). Youcan
secure the cables to these eyes with cable ties, for example.

Shield Contact

The cable duct and fan subassembly offer the facility of electrical contact for cable
shields. Youcan use the shield clamps provided
(see Reference Manual Module Specifications, Chapter 9).
Toestablish contact for the cable shields, strip the outer insulation in the region of
the shield clamp, and trap the cable shield under the shield clamp.
4.23 Routing Fiber-Optic Cables

Cable Routing

Indoor fiber-optic cables (for example, for connecting synchronization submodules)
are permitted for use in buildings, cable ducts, and channel trunking.
The maximum strain load when assembling is 1000 N and during operation 150 N.

Bending Radius

Minimum bending radius of the cables:
At the connector: 55 mm
Otherwise: 30 mm