4.Verify that local area network (LAN) preparations are completed (see
Section 2.2.1.2, “Local Network IP Addresses and Host Names Worksheet” on page 2-5).
5.Ensure that the host names and their network IP addresses are allocated and registered at the site. Record this information in TABLE
2.2.1.1Check Power, Thermal, Environmental, and Space Requirements
Observe that your environment meets the following requirements:
■Your enclosure specifications can support the sum of the specified maximum blade server power loads. (See Section A.2, “Power and Thermal Metrics” on page
■Facility power loading specifications can support the rack or enclosure requirements.
■Your enclosure specifications can support the cooling airflow requirements.
The Sun Netra CP3220 blade server fits into a standard ATCA shelf. If your installation requirements are different, contact your field applications engineer.