Trane RAUC-C30 manual Low Voltage Wiring AC & DC, Refrigerant Line Components, EVP Chiller Units

Models: RAUC-C20 RAUC-C40 RAUC-C25 RAUC-C30 RAUC-C60 RAUC-C50

1 112
Download 112 pages 31.47 Kb
Page 31
Image 31
Low Voltage Wiring (AC & DC)

Installation

Low Voltage Wiring (AC & DC)

WARNING

Hazardous Voltage!

Disconnect all electric power, including remote disconnects before servicing. Follow proper lockout/tagout procedures to ensure the power can not be inadvertently energized. Failure to disconnect power before servicing could result in death or serious injury.

Variable Air Volume (VAV) Units

[ ] Install a field provided remote system control switch to activate the system.

[ ] Connect properly sized wiring from the field provided economizer, if applicable, to the discharge air controller in the unit control panel.

[ ] Install and connect properly sized wiring from the night setback relay contacts to the proper termination points inside the unit control panel. Verify the appropriate jumpers have been removed.

[ ] Install the suction line thermostat onto the suction line. Connect properly sized wiring between the thermostat and terminal strip 7TB7 in the unit control panel.

[ ] Install the discharge air sensor and wire it to the discharge air controller with shielded cable.

EVP Chiller Units

[ ] Install the appropriate jumpers on the chilled solution temperature controller for hot gas bypass operation (If applicable). Refer to the control wiring diagram that shipped with the unit for jumper details.

[ ] Install and connect the chilled solution temperature sensor to the chilled solution temperature controller with shielded cable.

[ ] Install the proper staging resistor onto the chilled solution temperature controller.

Constant Volume Units

[ ] Install the zone thermostat, with or without switching subbase.

[ ] Connect properly sized control wiring to the proper termination points between the zone thermostat and the unit control panel.

[ ] Install the discharge air sensor and connect it to the master energy controller (MEC) with shielded cable.

[ ] Connect properly sized wiring from the field provided economizer, if applicable, to the master energy controller (MEC) in the unit control panel.

Refrigerant Line Components

Suction line refrigerant components necessary for field installation in the suction line are a filter (Core Type), access valves (ports), FrostatTM control for coil frost protection, and ball shutoff valves. They are placed in the suction line as illustrated in Figure 18.

The required liquid line refrigerant components include a filter drier (Core Type), access valve(s) or (ports), solenoid valve(s), moisture indicating sight glass, expansion valve(s), and ball shutoff valve(s). They are placed in the liquid line as shown in Figure 18.

Suction And Liquid Line Filter/Filter Drier (Field Supplied)

Install the filter in the suction line upstream of the compressors. It should be installed so the canister is at either a 45 or 90 degree angle to prevent oil accumulation.

Install the filter drier in the liquid line as close as possible to the expansion valves. Locate them upstream of the moisture indicator and solenoid valve.

SS-SVX09A-EN

31

Page 31
Image 31
Trane RAUC-C30 Low Voltage Wiring AC & DC, Refrigerant Line Components, Variable Air Volume VAV Units, EVP Chiller Units