Hazard of Explosion!

Installation

WARNING

Hazard of Explosion!

Never use an open flame to detect gas leaks. Explosive conditions may occur. Use a leak test solution or other approved methods for leak testing. Failure to follow recommended safe leak test procedures could result in death or serious injury or equipment or property-only-damage.

[ ] Leak test the system. Refer to the “Refrigerant Piping” section for recommended procedures.

EVP Chilled Water Piping Requirements

[ ] Install properly sized chilled water pipe between the EVP chiller and the supporting equipment. Refer to the “Chilled Water Piping” section for recommended system components and guidelines. Ensure that the recommended components have been installed:

Water pressure gauges (with isolation valves)

Thermometers

Chiller isolation (shutoff) valves in the solution inlet and outlet piping

Strainer in the solution inlet piping

Balancing valve

Flow switch in the solution outlet piping

Chilled solution sensor well and sensor in the solution outlet piping

Freezestat well and freezestat bulb in the chilled solution outlet piping

Chiller drain plug, or drain piping with a shutoff valve

[ ] Flushing the chilled solution piping system, if applicable.

Note: If using an acidic, commercial flushing solution, to prevent damage to the internal evaporator components, flush all chilled solution piping before making the final connection to the EVP chiller.

[ ] Connecting the chilled solution piping to the chiller.

[ ] Install heat tape and insulation, if necessary, to protect any exposed solution piping from external freezing conditions.

Main Electrical Power Requirements

WARNING

Hazardous Voltage!

Disconnect all electric power, including remote disconnects before servicing. Follow proper lockout/tagout procedures to ensure the power can not be inadvertently energized. Failure to disconnect power before servicing could result in death or serious injury.

[ ] Verify the power supply meets the required power requirements of the system.

[ ] Install power wiring in accordance with all applicable codes.

[ ] Install and connect properly sized power supply wiring, with over current protection, to the main power terminal block (1TB1) or to an optional factory mounted nonfused disconnect switch (1S1) in the control panel.

[ ] Install and connect properly sized power supply wiring, with over current protection, to the proper termination point in the air handling unit (If applicable).

[ ] Install and connect properly sized power supply wiring, with over current protection, to the proper termination point for the chilled solution pump (EVP units only).

28