15 – Cabinet Installation (continued)

15 – Cabinet Installation (continued)

 

 

5-3 Placement

 

 

 

 

Use the casters to move the UPS system for a short distance over

2

 

1

 

 

a level, smooth, stable surface. Do not attempt to use the casters

 

 

 

to move the UPS system over longer distances. The UPS system

 

 

 

should be moved close to its final installation location inside

 

 

 

 

its shipping container before it is unpacked from the shipping

 

3

 

 

container. Use a mechanical device of sufficient capacity to move

 

 

the shipping container. Warning: The UPS system could tip if it

 

 

 

is moved over an unstable surface. Be extremely careful when

 

 

 

moving the UPS system. Push the UPS system from the front or

 

 

 

 

rear, not from the sides.

4

 

 

Position the UPS system in a structurally sound area with a

 

2

 

 

 

level floor that is able to bear the weight of the UPS system,

 

 

 

any external battery cabinets and other equipment that will be

 

 

 

 

installed nearby. The installation site should also have a dedicated

5

 

 

AC circuit available that is compatible with the UPS system’s

 

 

input requirements. (See the Section 12 – Specifications for

 

 

 

 

 

 

more information about input requirements and floor loading

 

 

 

requirements.) The UPS system must be installed in a clean,

 

 

 

 

secure environment with a relative humidity less than 90% (non-

6

 

 

condensing). Operate the UPS system at indoor temperatures

 

 

between 17° C and 29° C (62° F and 84° F). Prevent damage to

 

 

 

 

 

 

cabling by using suitable protective conduits. In order to maintain

 

 

 

proper airflow and service access, you must maintain the following

 

 

 

clearances:

7

 

 

• At least 100 cm (39.4”) clearance in front of the UPS system.

At least 50 cm (19.7”) clearance behind the UPS system.

At least 50 cm (19.7”) clearance above the UPS system.

8

 

Warning: The cooling fans circulate air from front to back. Do not

 

 

use any air conditioning or fan that blows air directly toward the

 

 

rear of the UPS system.

 

 

 

 

After moving the UPS system to its final location, lock the casters

 

 

3

9

 

 

 

A

and use the levelers

B

to stabilize the cabinet. Ensure that all

 

 

 

four levelers make firm contact with the floor.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10

 

 

 

 

 

 

 

 

 

 

 

For emergency use, install a fire extinguisher rated for energized

 

 

 

 

11

 

4

 

 

 

 

 

 

electrical equipment fires (Class C rating or exact equivalent, with

a non-conductive extinguishing agent) near the UPS system.

12

13

14

1

50 cm (19.7”)

50 cm (19.7”)

100 cm (39.4”)

2

B

A

3

 

4

10

Page 10
Image 10
Tripp Lite SU20KX 1 5 - Cabinet Installation continued, Placement, rear, not from the sides, rear of the UPS system