CHECKING THE SYSTEM SHUTDOWN CIRCUIT

Procedure

1)With the system operating, momentarily depress the System Shutdown pushbutton located on the power and control sub-rack.

2)Verify that the rectifier module AC input circuit breakers located on the power and control sub-rack and the battery circuit breaker located on the internal battery trays open.

3)Restart the system by first turning ON the rectifier module AC input circuit breakers then the battery circuit breaker(s).

CHECKING SYSTEM STATUS

Procedure

1)Observe the status of the indicators located on the ACU+ Controller, rectifier modules, and power and control sub-rack. If the system is operating normally, the status of these is as shown in Table 5-2.

 

Component

 

Indicator

 

Normal State

 

 

 

 

 

 

 

 

 

 

Status

 

 

On

 

 

 

(Green)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ACU+

 

Information

 

 

Off

 

 

(Yellow)

 

 

 

Controller

 

 

 

 

 

 

 

 

 

 

 

Warning or

 

 

 

 

 

 

 

 

 

 

 

 

Critical Alarm

 

 

Off

 

 

 

(Red)

 

 

 

 

 

 

 

 

 

 

 

 

 

Power

 

 

On

 

 

 

(Green)

 

 

 

 

 

 

 

 

 

Rectifier

 

 

 

 

 

 

 

Protection

 

 

Off

 

Modules

 

(Yellow)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Alarm

 

 

Off

 

 

 

(Red)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Output Voltage

 

On

 

 

 

Present (Green)

 

 

 

 

 

 

 

 

 

 

 

 

 

Power and

 

PS1 Indicator (Green)

 

On

 

Control

 

PS2 Indicator (Green)

 

On

 

Sub-Rack

 

Ground Fault Alarm

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(HRMG Configurations Only)

 

Off

 

 

 

(Red)

 

 

 

 

 

 

 

 

 

 

 

Table 5-2

 

 

 

 

Status and Alarm Indicators

 

Page 50

Chapter 5. Initially Starting the System

This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy

Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.

Image 60
Contents Installation Instructions IM584000300 Issue AB, April 3Page Table of Contents Issue AB, April 3 Spec. No Model General Safety Important Safety InstructionsVoltages AC Input Voltages DC Input/Output VoltagesBattery if Equipped Personal Protective Equipment PPE Maintenance and Servicing Procedures Dual Hazardous Input Power SourcesCircuit Card Handling GeneralStatic Warning IM584000300 Bound System Installation Manual Customer Documentation PackageSystem Packaging USB Drive with All Customer DocumentationPower and Control Sub-Rack List 11 Temperature Probes List 98 Part Number QtyGeneral Part Number Qty Rectifiers Part Number QtyDC Load Distribution Sub-Rack List 21, 22, 23 Battery Tray List 91 Recommended Tools and Test Equipment Installation Acceptance Checklist Checklist -Factory Integrated System List R1, R2General Checklist Customer Integrated System ship loose Air Flow Diagram Installing the System General RequirementsAir Flow Inspecting the Equipment Storing for Delayed Installations Storing for Delayed InstallationSecuring the IT Rack to the Floor Inspecting the EquipmentInstalling Individual SUB-RACKS Into Cutomer Installing the Sub-RacksFor customer provided IT rack installation only Customer Supplied IT Rack GuidelinesIM584000300 Electrically Interconnecting the Sub-Racks Mounting DetailsImportant Safety Instructions Wiring Considerations Output Ground ConfigurationsTorque Cable RoutingSub-Rack IM584000300 Removable Panel Hrmg Configurations Only Bus Grounding Connection Tasks to be Performed for Customer Integrated SystemsGrounding Sub-Rack Grounding Frame GroundIssue AB, April 3 Spec. No Model Load Distribution Sub-Rack Battery TrayLoad Distribution Sub-Rack Power and Control Sub-Rack Sub-Racks Electrical Interconnections Sub-Rack Interconnections Making Electrical Connections Power and Control Sub-Rack Battery Tray Tasks to be Perform for ALL Installations IT Rack Grounding Frame GroundConduit Grounding Frame Ground Grounding Scheme Diagram Hrmg System GroundingNPG System Grounding Suggested AC Input Power Connections AC Input Power Connections Making Electrical ConnectionsHrmg High Resistance Midpoint Ground Configuration NPG Negative Pole Ground ConfigurationLoad Distribution Sub-Rack Battery Manufacturer Information Installing Battery Sub-TraysRefer to -12as this procedure is performed Battery Sub-Trays External Battery Connections if required External Battery Connections Making Electrical Connections Customer Connection To External Battery StringsIB2 ACU+ Controller Interface Board Connections if required Digital Inputs and Programmable Relay OutputsDigital Inputs Programmable Relay OutputsInstallation Instructions Issue AB, April 3 Spec. No Model Temperature ProbesACU+ Controller Ethernet Connection if required Power and Control Sub-Rack Programmable J6-5 J6-3 None J6-1 J6-6J6-4 None J6-2 J7-5 J7-3 None J7-1 J7-6Power and Control Chapter Installing the Rectifier Module Initial Startup Preparation Circuit Breaker Locations Initially Starting the SystemInitially Starting the System ACU+ Controller Local Indicators and Navigation Keys ACU+ Controller InitializationVersion ***** Starting… IM584000300 Verifying the Configuration File Changing Battery Capacity Rating in the ACU+ Checking Basic System Settings Procedure To Select a Sub-Menu To Enter a Password To Change a ParameterPage Configuring the ACU+ Identification of Rectifiers Checking the System Shutdown Circuit Checking System StatusFinal Steps Reference DocumentsChange Issue Number Description of Change ECONetPerform Optimization Services For More Information