Emerson 4015 ACU+ Controller Initialization, ACU+ Controller Local Indicators and Navigation Keys

Page 54

IM584000300

Installation Instructions

Issue AB, April 3, 2013

Spec. No. 584000300 (Model 4015-X003)

 

 

ACU+ CONTROLLER INITIALIZATION

Note: For factory configured systems, your controller was programmed with a configuration file that sets all adjustable parameters. Provided on a USB drive furnished with the system is an ACU+ configuration drawing (C-drawing) and the ACU+ configuration files loaded into the ACU+ as shipped. If ordered for customer integration, you will have to program the controller for your application per step 8) below.

Refer to the ACU+ Controller Operation Instructions (UM1M820NNB-1) for detailed instructions.

Refer to Figure 5-2for locations of the ACU+ local indicators and navigation keys.

Information Alarm

Indicator (Yellow)

10/100M Ethernet Port (RJ-45)

USB Port

Status

Warning or Critical

Indicator

Alarm Indicator

(Green)

(Red)

ESC

ENT

Menu Navigation Keys

Figure 5-2

ACU+ Controller Local Indicators and Navigation Keys

Procedure

Note: The initialization routine takes several minutes. During that time various alarm indicators may illuminate on the ACU+ front panel and an audible alarm may sound. Disregard all alarms. An audible alarm can be silenced at any time by momentarily depressing the ENT key on the ACU+ Controller.

1)After the ACU+ is powered on, the display alternates between the “Emerson Network Power” screen and a screen displaying “Advanced Control Unit Plus

Version ***** Starting…”.

Page 44

Chapter 5. Initially Starting the System

This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy

Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.

Image 54
Contents Installation Instructions IM584000300 Issue AB, April 3Page Table of Contents Issue AB, April 3 Spec. No Model Voltages General SafetyImportant Safety Instructions AC Input Voltages DC Input/Output VoltagesBattery if Equipped Personal Protective Equipment PPE Circuit Card Handling Maintenance and Servicing ProceduresDual Hazardous Input Power Sources GeneralStatic Warning IM584000300 System Packaging Bound System Installation ManualCustomer Documentation Package USB Drive with All Customer DocumentationGeneral Part Number Qty Power and Control Sub-Rack List 11Temperature Probes List 98 Part Number Qty Rectifiers Part Number QtyDC Load Distribution Sub-Rack List 21, 22, 23 Battery Tray List 91 Recommended Tools and Test Equipment Installation Acceptance Checklist Checklist -Factory Integrated System List R1, R2General Checklist Customer Integrated System ship loose Air Flow Diagram Installing the System General RequirementsAir Flow Securing the IT Rack to the Floor Inspecting the Equipment Storing for Delayed InstallationsStoring for Delayed Installation Inspecting the EquipmentFor customer provided IT rack installation only Installing Individual SUB-RACKS Into CutomerInstalling the Sub-Racks Customer Supplied IT Rack GuidelinesIM584000300 Electrically Interconnecting the Sub-Racks Mounting DetailsTorque Important Safety Instructions Wiring ConsiderationsOutput Ground Configurations Cable RoutingSub-Rack IM584000300 Removable Panel Grounding Hrmg Configurations Only Bus Grounding ConnectionTasks to be Performed for Customer Integrated Systems Sub-Rack Grounding Frame GroundIssue AB, April 3 Spec. No Model Load Distribution Sub-Rack Battery TrayLoad Distribution Sub-Rack Power and Control Sub-Rack Sub-Racks Electrical Interconnections Sub-Rack Interconnections Making Electrical Connections Power and Control Sub-Rack Battery Tray Tasks to be Perform for ALL Installations IT Rack Grounding Frame GroundConduit Grounding Frame Ground Grounding Scheme Diagram Hrmg System GroundingNPG System Grounding Suggested AC Input Power Connections AC Input Power Connections Making Electrical ConnectionsHrmg High Resistance Midpoint Ground Configuration NPG Negative Pole Ground ConfigurationLoad Distribution Sub-Rack Battery Manufacturer Information Installing Battery Sub-TraysRefer to -12as this procedure is performed Battery Sub-Trays External Battery Connections if required External Battery Connections Making Electrical Connections Customer Connection To External Battery StringsDigital Inputs IB2 ACU+ Controller Interface Board Connections if requiredDigital Inputs and Programmable Relay Outputs Programmable Relay OutputsInstallation Instructions Issue AB, April 3 Spec. No Model Temperature ProbesACU+ Controller Ethernet Connection if required Power and Control Sub-Rack Programmable J6-4 None J6-2 J7-5 J6-5J6-3 None J6-1 J6-6 J7-3 None J7-1 J7-6Power and Control Chapter Installing the Rectifier Module Initial Startup Preparation Circuit Breaker Locations Initially Starting the SystemInitially Starting the System ACU+ Controller Local Indicators and Navigation Keys ACU+ Controller InitializationVersion ***** Starting… IM584000300 Verifying the Configuration File Changing Battery Capacity Rating in the ACU+To Enter a Password Checking Basic System SettingsProcedure To Select a Sub-Menu To Change a ParameterPage Configuring the ACU+ Identification of Rectifiers Checking the System Shutdown Circuit Checking System StatusFinal Steps Reference DocumentsChange Issue Number Description of Change ECONetPerform Optimization Services For More Information