SOLA 4000 - Installation and Initial Start-Up
1 Installation
1.12 Battery Installation
Battery Installation must be in accordance with local safety standards.
General The batteries are charged. The installation should only be made by appropriately qualified personnel. The screw connections between the batteries should be tightened with a torque wrench (max. 7 Nm).
1.12.1Installation of Internal batteries SOLA 4000
Internal Battery (24Ah) Installation
•Place five battery blocks on the trays of the first level.
•Place nine battery blocks on the trays of the second, third and fourth level.
•Interconnect the blocks in series (see FIG.1.12.1)
Warning: after assembly there is a voltage of 67,5 V on the first level, and 121,5 V on the second, third and fourth levels.
1° LEVEL
2° LEVEL
3° LEVEL
4° LEVEL
JUE 401265 | 42 |