Operation

To select automatic transfer operation, do the following:

1A. For models 071018 & 071019, set disconnect switch that sends utility power to transfer switch to “On” position. This switch is probably located in the main breaker panel.

1B. For models 071020 & 071021, set utility breaker in transfer switch “On” position.

2.Set generator main circuit breaker to its “On” position.

3.Install 15 Amp fuse in generator control panel.

4A. If generator is equipped with a system ON/OFF switch, set switch to “On” position.

4B. If generator is equipped with a AUTO/OFF/MANUAL switch, set switch to “AUTO” position.

The system will now be in automatic operation mode.

When the generator is providing power to the transfer switch, the control module is constantly monitoring generator power. If the air conditioner is called to run, and there is sufficient generator power available, the control module will close contacts “A-A” to air conditioner contactor. Contacts “B-B” will open before contacts A-A close. If loads are too great for generator, contacts A-A and/or B-B will open. When air conditioning is not needed, A-A will open. If enough power is available, B-B will close.

Testing the Automatic Transfer Switch

Turn the disconnect switch feeding the transfer switch contactor to the “Off” position. The Automatic Sequence of the system will follow. To go back to utility power, turn the disconnect to the “On” position.

Automatic Sequence

Utility Fail

The Home Standby Generator set senses when utility voltage is below 70 percent of nominal. Engine start sequence is initiated after 6 second time delay.

Engine Warm-Up

Time delay to allow for engine warm-up before transfer fixed at 20 seconds or 50 seconds with removal of jumper on control board (see System Setup).

Transfer

Transfer from utility to generator supply occurs after voltage is above set levels. Minimum engine run time is 5 minutes after transfer.

Utility Pickup

Voltage pickup level is 80 percent of nominal voltage.

Retransfer

Retransfer from generator to utility supply is approximately 10 seconds after utility voltage supply is above utility pickup level and minimum run time is completed.

Engine Cool Down

Engine will run for 60 seconds after retransfer.

When Calling the Factory

Before contacting Briggs and Stratton Power Products regarding service or repair of this transfer switch, obtain the Model Number and Serial Number from the unit data decal located on or inside the enclosure.

To contact Briggs and Stratton Power Products call

1-800-743-4115, between 8:00 AM and 5:00 PM CT.

8

BRIGGSandSTRATTON.COM

Image 10
Contents Call Transfer Switch Helpline BRIGGSandSTRATTON.COM 100 AMP/200 AMPTransfer Switch Where to Find UsDate Purchased Table of Contents Important Safety Instructions For the Home Owner Installer ResponsibilitiesIntroduction Owner OrientationUnpacking InstallationShipment Contents Mounting GuidelinesAlternate Transfer Switch Mounting Power Wiring Interconnections Utility ConnnectionSystem Setup Supervisory Control WiringControls Operation Testing the Automatic Transfer SwitchWhen Calling the Factory Automatic SequenceUL 1008 Listed Transfer Switch Model MaintenanceSpecifications Supervisory Contacts RatingTroubleshooting Problem Cause CorrectionSchematic and Wiring Diagram, Models 071018 Schematic and Wiring Diagram, Models 071020 Description Illustrated Parts List, ModelItems Not Illustrated 192166GS ENCLOSURE, 22 x 16 x 197355GS CLIP, Latching Wire192597GS DECAL, Utility 240VAC 196094GS WASHER, Lock 1/4 190984GS DECAL, FuseASSY, Enclosure 196520GS 193159GS DECAL, Reinstall Barrier 192151GS197355GS CLIP, Latching Wire DECAL, UL Listed192879GS INSULATION, Circuit Breaker 196094GS 197355GS CLIP, Latching Wire 195728GSASSY, Enclosure 196521GS 197294GS DECAL, Contacts Rating WASHER, Lock 1/4 192881GSLimited Warranty Reserved Manual de Instalación Del Operario Conectador Automático Dónde puede encontrarnosFecha de compra Mantenimiento MandosEspecificaciones Conserve estas instrucciones Instrucciones importantes de seguridadOrientación para el Propietario IntroduccionPara el Propietario Doméstico Responsabilidades del InstaladorPautas de Montaje InstalacionDesempaque Inspección al Momento de la EntregaFigura 2 Montaje de un Conectador Alternativo Interconexiones de Cableado de Energía Configuración del Sistema Cableado de Control de SupervisiónPrueba del conectador automático MandosSistema Funcionamiento Secuencia AutomáticaUL 1008 Listó Conectador Modelo MantenimientoEspecificaciones Carga máxima/circuitoReparacion de AveriasGarantía Garantía Limitada Reserved Guide dInstallation Et dUtilisation Commutateur de Transfert Où nous trouverDate d’achat Entretien Commandes FonctionnementMise à lessai du commutateur de transfert automatique CaractéristiquesDirectives de sécurité importantes Instalación FonctionnementCommandesVeuillez conserver ces instructions SécuritéAu Propriétaire Résidentiel Responsabilités de lInstallateurIntroduction Conseils au PropriétaireInstalation Consignes dinstallationInstalación Commandes Vérification de la Livraison DéballageIté Etien Interconnexions du câblage dalimentationIté RantieConfiguration du système Câblage de contrôleMise à lessai du commutateur de transfert automatique CommandesFonctionnement Séquence AutomatiqueUL 1008 Enuméré Commutateur de Transfert Modéle EntretienCaractéristiques ModèleDepannage Garantie Limitée