Figure 3.9-3 shows the alarm output connection designations. Whenever possible use the common and normally closed contacts. If the alarm wiring gets pulled loose, or the controller is removed, you will get an alarm. The Major relay is energized (C-NO contacts closed) during normal (non-alarm) operating conditions; the other relays energize when an alarm condition occurs. If your Major relay wiring uses the C-NO contacts, then a major relay output will be seen whenever the controller is removed from the shelf.

Output Relays (J411)

User Inputs (J412)

Figure 3.9-1 Interface Connections

Output Relay 2-6 Connections

Output Relays 2 through 6 are virtual relays and are not available for physical connection by the user. The small size of this unit limits the number of relays that can be placed in the system. These output relays are supported by the controller and reported by the network management card. Any alarm condition can be programmed to map to one of these relays. The alarm will activate the relay, illuminate the front panel Out Relay LED, and send the relay output message to the network management card.

RELAY

 

J 411 TERMINAL

 

RELAY ALIAS

OUTPUT RELAY NOTES

OUTPUT

 

DESIGNATIONS

 

 

 

 

 

 

NO

 

 

 

OUT RELAY #1

 

 

C

 

 

 

 

 

 

NC

 

 

 

OUT RELAY #2

 

 

N/A

 

 

 

OUT RELAY #3

 

 

N/A

 

 

 

OUT RELAY #4

 

 

N/A

 

 

 

OUT RELAY #5

 

 

N/A

 

 

 

Magnum VS –48 Vdc User’s Manual

Page 13

Image 18
Contents Magnum VS Vdc Power Systems User’s Manual Table of Contents Final Inspection TWF0500H54B Rectifier Magnum VS Controller Revision History Document # & Rev Date DescriptionSafety First General PrecautionsHow to Use This Manual IntroductionGeneral Information Amp System Only Unpacking Equipment InstallationMechanical Installation Room / LocationAC Power Connections VentilationAC Connections AC Power Cord Sets AWGBattery Connections Planning the Battery installationConnecting the Cables Battery Temperature Probe Installation 1 Battery Cable Connection LocationsCounter Electro-Motive Force Cemf Cell Connections DC System GroundingLoad Protection Installation Circuit Breaker InstallationGMT Fuse Installation Circuit Breaker Protected Load Connections 30 or 60 a Load ConnectionsCable Size Considerations GMT Fuse protected Load ConnectionsFront Panel DB9 Connection RJ45 Ethernet ConnectorMonitoring and Relay Output Connections Major, Minor and Relay 1 Output ConnectionsOutput Relay 2-6 Connections Relay Terminal Relay Alias Output Relay Notes DesignationsRectifier Module Installation External Alarm Input ConnectionsController Module Installation Commissioning Electrical InstallationBattery Visual and Safety Inspection Pre-Commissioning InspectionCommissioning AC Power UpDC Power Up Initial Set-upLVD Test Battery Power UpRectifier Test Circuit Breaker/ Fuse TestBattery Temperature Compensation Final InspectionOutput Relay Technical Description Rectifier ManagementSystem Management System Current Monitor System Status and Alarm ReportingLoad Management Circuit BreakersBattery Management Battery ChargingGMT Fuses Battery Equalization Battery ProtectionBattery Temperature Monitoring Battery Low Voltage Disconnect Battery Functional TestCounter Electro-Motive Force Module Connections Controller with Display Controls and IndicatorsAlarm Outputs Output Relays Controller without DisplayExternal Alarm Inputs User Input Network Management Card Local & Remote MonitoringOperation DescriptionController Card Jumpers Controller with Display J12 J13Operation using Local Display and Keypad Interface 1 Controller with Display设置 / 电池 / 容量 设置 / 系统 / 时/日 均充 / 均充时间 状态 / 系统 /参数 Alarms 均充时间 Operation Using the RS-232 Comm Port Controller without DisplayOperation Using the 10/100 BaseT Ethernet Port 1 Parameter Locations, Descriptions, and Settings ON, OFF Power Modules/Rectifiers Seconds Disable Output Relay LVD Operation System/PreferencesProgramming Output Relays Page Equipment Preventive MaintenanceSystem Visual and Safety Inspection InspectionSystem Voltage Test Rectifier Alarm TestTest Rectifier Current Share TestSystem Temperature Test Battery Current TestBattery Temperature Test Battery Preventive Maintenance Procedure Alarm Summary System LT Alm System Temperature is below Minor AC Input SpecificationsMagnum VS 50 Power System TWF0500H54B RectifierMagnum VS 100 Power System DC OutputMagnum VS 50 Power System Mechanical Magnum VS ControllerEnvironmental Compliance EMCAPC Worldwide Customer Support Limited Product Warranty