8.Check that anti-oxidation compound is properly applied.

9.Visually inspect each cell for:

a.Cracks.

b.Case leaks.

c.Post-seal leaks.

d.Pressure relief valve leaks (VRLA only).

e.Case swelling (VRLA only).

10.Check the torque of all battery inter- cell connector in accordance with the battery manufacturer’s specifications.

4.2. Commissioning

Initial Set-up

1.Remove all rectifiers.

2.Disconnect battery by removing a link in each string or opening the battery disconnects.

3.Check that battery voltage does not appear on the system bus.

4.Disconnect all loads.

AC Power Up

WARNING: The dc power plant is supplied from a nominal high voltage ac voltage source. Keep the ac input enclosure cover in place when the system is operational or energized

1.Verify that all of the circuit breaker positions are labeled to the corresponding rectifier correctly.

2.Insert all rectifiers.

3.Turn all rectifier circuit breakers on.

4.Each rectifier should have green Input Healthy and Output Healthy LEDs illuminated.

NOTE: When ac power is initially applied, there is a 60-second period during which no alarms are reported.

DC Power Up:

1.Verify with a voltmeter that the dc voltage is within 0.1 Vdc of the System Voltage

2.Adjust battery float voltage to negative 49 Vdc.

3.Verify System Low Voltage Alarm.

4.Adjust battery float voltage to negative 57 Vdc.

5.Verify System High Voltage Alarm.

6.Restore the battery float voltage to negative 54.00 Vdc or desired voltage.

Magnum VS –48 Vdc User’s Manual

Page 17

Image 22
Contents Magnum VS Vdc Power Systems User’s Manual Table of Contents Final Inspection TWF0500H54B Rectifier Magnum VS Controller Revision History Document # & Rev Date DescriptionSafety First General PrecautionsIntroduction How to Use This ManualGeneral Information Amp System Only Unpacking Equipment InstallationMechanical Installation Room / LocationVentilation AC Power ConnectionsAC Connections AC Power Cord Sets AWGPlanning the Battery installation Battery ConnectionsConnecting the Cables Battery Temperature Probe Installation 1 Battery Cable Connection LocationsCounter Electro-Motive Force Cemf Cell Connections DC System GroundingCircuit Breaker Installation Load Protection InstallationGMT Fuse Installation Circuit Breaker Protected Load Connections 30 or 60 a Load ConnectionsCable Size Considerations GMT Fuse protected Load ConnectionsFront Panel DB9 Connection RJ45 Ethernet ConnectorMonitoring and Relay Output Connections Major, Minor and Relay 1 Output ConnectionsOutput Relay 2-6 Connections Relay Terminal Relay Alias Output Relay Notes DesignationsRectifier Module Installation External Alarm Input ConnectionsController Module Installation Commissioning Electrical InstallationBattery Visual and Safety Inspection Pre-Commissioning InspectionCommissioning AC Power UpDC Power Up Initial Set-upLVD Test Battery Power UpRectifier Test Circuit Breaker/ Fuse TestFinal Inspection Battery Temperature CompensationOutput Relay Rectifier Management Technical DescriptionSystem Management System Current Monitor System Status and Alarm ReportingLoad Management Circuit BreakersBattery Charging Battery ManagementGMT Fuses Battery Protection Battery EqualizationBattery Temperature Monitoring Battery Functional Test Battery Low Voltage DisconnectCounter Electro-Motive Force Module Connections Controller with Display Controls and IndicatorsAlarm Outputs Output Relays Controller without DisplayExternal Alarm Inputs User Input Network Management Card Local & Remote MonitoringDescription OperationController Card Jumpers Controller with Display J12 J13Operation using Local Display and Keypad Interface 1 Controller with Display设置 / 电池 / 容量 设置 / 系统 / 时/日 均充 / 均充时间 状态 / 系统 /参数 Alarms 均充时间 Operation Using the RS-232 Comm Port Controller without DisplayOperation Using the 10/100 BaseT Ethernet Port 1 Parameter Locations, Descriptions, and Settings ON, OFF Power Modules/Rectifiers Seconds Disable Output Relay LVD Operation System/PreferencesProgramming Output Relays Page Equipment Preventive MaintenanceSystem Visual and Safety Inspection InspectionSystem Voltage Test Rectifier Alarm TestTest Rectifier Current Share TestBattery Current Test System Temperature TestBattery Temperature Test Battery Preventive Maintenance Procedure Alarm Summary System LT Alm System Temperature is below Minor AC Input SpecificationsMagnum VS 50 Power System TWF0500H54B RectifierMagnum VS 100 Power System DC OutputMagnum VS 50 Power System Mechanical Magnum VS ControllerEnvironmental Compliance EMCAPC Worldwide Customer Support Limited Product Warranty