Setting Up the System

Setting the Number of Stations and the Number of Pumps

1.Touch System Setup at the Station Status (or Pump Status) screen. The System Setup screen appears:

Note: Touching Help in the lower right of this screen gives you a menu of online help for the choices in this screen.

2.Touch Stations Present in the upper left of the System Setup screen.

3.This will take you to the Stations Installed screen.

A screen showing a list of stations appears. The stations that are not installed are red. The stations that are installed are green. Briefly touching the icon for a station toggles between not installed and installed.

4.Press System Setup to return to the System Setup screen.

5.Touch Pumps Present in the upper part of the System Setup screen.

6.This will take you to the Pumps Installed screen.

The screen shows a list of pumps. The pumps that are not installed are red. The pumps that are installed are green. Briefly touching the icon for a pump toggles between not installed and installed.

7.Press System Setup to return to the System Setup screen.

24-Pump, 128-Station Controller

Chapter 3: Installation

37

Image 38
Contents SCC 24-Pump 128-Station Controller Parts and Service Department Shipping Information Table of Contents Maintenance Safety Symbols Used in this Manual SafetyHow to Use This Manual Wear Safety Glasses and Work Gloves Operator Responsibility ResponsibilityGeneral Responsibility Maintenance Responsibility Reporting a Safety DefectFunctional Description Standard FeaturesMechanical Features Models Covered in This ManualElectrical Features Optional FeaturesSafety Devices and Interlocks Controller FeaturesFail Safe Operation Safety Circuit StandardsSafety Device Lock-Outs Uncrating InstallationSystem Installation Overview Mounting the Control PanelElectrical Connections Making Control Panel Power Drop Wiring ConnectionsInstalling KwikLink Cable Running KwikLink CablesSetting Up and Installing Mounting Plates Setting Up Mounting PlatesInstalling Assembled Mounting Plates Terminating Cable RunsInstalling Inside KwikLink Connectors with Blank Caps Discard the standard resistor cap to eliminate confusionArmorBlock Address Ranges Addressing and Installing ArmorBlocksAddressing ArmorBlocks Setting ArmorBlock Addresses Using seal block to pierce cable Installing KwikLink Connectors Connecting the Controller to the Network Connecting the Remote Interface to the Main ControllerPage Connecting the Power Supply Enclosure to the Network Proper Controller and Remote Interface ConnectionsPage Proper Power Supply Enclosure Connections Connecting Vacuum Receivers to the Network24/128 8-Connector ArmorBlock Connections Proper Vacuum Receiver Connections Connecting Vacuum Pumps and Filter Chambers to the Network Connecting Vacuum PumpsProper Vacuum Pump Connections, Standard XPD/XPC Pumps Proper Vacuum Pump Connections, Xpdb Pump Connecting Filter Chambers Proper Filter Chamber Connections, Blowback Proper Filter Chamber Connections, Implosion Type Connecting Central Alarms to the Network Proper Central Alarm Connections Setup Connector ArmorBlock Connections for Central AlarmsSetting Up the System Setting the Number of Stations and the Number of PumpsNaming Purge Valves and Materials Setting the Date/TimeChecking Addressing and Wiring for System Components Setting Up Alarm Silences Alarm Horn Silence Setting Up Pump StagingSetting Up Stations Setting Up a Single StationNaming Stations Copying Settings from One Station to Others To copy the selected station’s settings to one other stationSetting Up Pumps Setting Up a Single PumpPage Copying Settings from One Pump to Others Naming PumpsTo copy the selected pump’s settings to one other pump To copy the current pump’s settings to all other pumpsFinishing Setup Setting Up Passwords Password Duration Save/Restore SettingsInitial Startup Starting and Stopping the System OperationOverview Basic Tasks Reviewing Station StatusReviewing Pump Status Color Label DescriptionLogging On and Logging Off Enter the alphanumeric password Enabling and Disabling Stations and PumpsNavigating among the Station Operator Screens Reviewing and Adjusting Basic Station SettingsReaching and Reading the Station Operator Screens Adjusting Convey Time and Dump Delay Activating and Stopping Priority Convey for a StationChanging the Mixture for a Remote Proportioning Valve Transferring Stations to a Standby Pump Reviewing and Resetting a Pump Hour MeterAdvanced Tasks Page Page Silencing Alarms AlarmsReviewing Alarms Corrective Maintenance MaintenancePreventative Maintenance Network Scanner Module ConsiderationsMemory Module Considerations Configurable SettingsOptions for Station Setup Name Description Options Default Conveying Options Option Input Pump, 128-Station Controller Configurable Settings Pump, 128-Station Controller Configurable Settings Options for Pump Setup Pump, 128-Station Controller Configurable Settings Troubleshooting General TroubleshootingStation Alarms Alarm message Possible causePump, 128-Station Controller Troubleshooting Pump Alarms System AlarmsOptional Components WarrantyAppendix Drawings and Diagrams 24-Pump, 128-Station Controller with 10 DisplaySpare Parts List Typical System Installation LayoutCredit Returns Warranty ReturnsReturned Material Policy Controller Identification Serial Number Tag Safety Tag InformationController Safety Tags Parts Department Service DepartmentTechnical Assistance Contact Information Sales Department