GTO RB923 rev Preparing the Gate, Pull-to-Open Single Gate gate opens into the property, Step

Page 14

Single Gate Operator Installation

Pull-to-Open Single Gate (gate opens into the property)

The diagram below is an example of a single leaf, pull-to-open installation on an ornamental iron gate. If you are installing a Push-to-Open(gate opens out from the property) system, see page 31. Or, if you are mounting the operator on a masonry column, please refer to page 36 before proceeding.

 

Receiver

 

Control Box with

Post Bracket Assembly

 

Battery

 

120 Volt Indoor

 

Warning Sign

Transformer

Gate Bracket

 

 

 

(surge protector

GTO/PRO 2000

 

not supplied)

 

 

Run 1000' (max.) of low

Power Cable

Closed Position Positive Stop Plate

voltage wire to control

 

 

box from transformer.

 

 

(wire not included)

 

 

 

PVC conduit (not included) to protect wire from lawn mowers and weed eaters.

Preparing the Gate

Step 1:

The gate must be in proper working order, plumb, level and swinging freely on its hinges. Do not use wheels on gate. The gate must move smoothly and evenly throughout its swing, without binding or dragging on the ground. Gates over 250 lb. should have ball bearing hinges with grease fittings.

Step 2:

The fence post must be strongly secured in the ground with concrete so it will not twist or flex when the operator is powered. It is important to position the operator near the midline of the gate to keep the gate from twisting and flexing. The addition of a horizontal or vertical cross member may be necessary (if one is not already in place) to provide a stable area to which the gate bracket can be secured.

For the operator to perform properly, Steps 1 & 2 must be complete before you go any further with the installa- tion.

Horizontal Cross Member

Vertical Cross Member

11

Image 14
Contents Series Converting Temperature Table of Contents Important Safety Instructions Disconnecting the OperatorBefore Installation II. During InstallationIII. After Installation Entrapment Alarm UL 325 30A.1.1A Secondary Means of Protection Against EntrapmentConsumer/End User No ONE should Cross the Path of the Moving GateEntrapment Protection Required Safety Precautions for Swing GatesInstall Warning Signs Moving Gate Can Cause Injury Or Death Technical Specifications GTO/PRO 2000 Series Swing Gate OperatorsParts Hardware not to scaleSingle Gate Operator Parts List Control Box and Electrical ComponentsStep Preparing the GatePull-to-Open Single Gate gate opens into the property Installing The Post Bracket Assembly Step Rear mount bolt, leave it loose Connecting Operator to Post Bracket Assembly1/ nut. Note when tightening Enough for the operator to pivotInstalling the Gate Bracket Installing the Open and Closed Position Stops Mounting the Control Box Never insert the battery with the terminals to the right BatteryPowering the System Gate LengthEstimated Maximum Number of Cycles Per Day Splice wires togetherSolar Zones and Gate Activity Make sure the exposed wires do not touch each other Not touch each otherControl Board Settings DIP SwitchesPotentiometers Remove the Transmitter Cover Setting the Personal Transmitter CodeSet the transmitter DIP Switches Run the cable through PVC conduit to protect it from damage Mounting the ReceiverMemory For Push-to-Open Installations Setting the Closed Position Limit SwitchStep For Pull-to-Open Installations Step Connecting Additional Safety Devices Photoelectric Beams Compatible Safety DevicesSafety Edges BLU blue used with GRN green Connecting AccessoriesWHT white used with GRN green ORG orange used with GRN greenStep PTO-2 Push-to-Open InstallationStep PTO-1 Step PTO-5 Step PTO-3Step PTO-4 Step PTO-6Maintenance and Troubleshooting Guide MaintenancePage GTO, Inc., 3121 Hartsfield Road, Tallahassee, Florida, USA Warranty and Repair ServiceLimited Two Year Warranty Column Installation Information Second Unit Parts List GTO/PRO 2200 Dual Gate SystemStep D1 Installing The Second UnitGTO Automatic Gate Lock see Accessory Catalog StepD2Step D-4 Connecting the Second Operator to the Control BoardStepD3 Step D-5Step D-8 Setting the Control Board for Dual Gate InstallationsStep D-7 Step D-9Step D-11 GTO Nema Box FM317 Accessories Available Through Your DealerRB101 RB509 ACCESS-ories433IH Master Pin Lock RB975Access -ories Replacement BatteriesInstallation Check list Installation of this operator conforms to Class