Installing The Second Unit

The diagram below shows a dual gate, pull-to-open (gate opens into the property) installation on iron gates.

If you are installing a Push-to-Open (gate opens out) system see Push-to-Open Installation starting on page 31.

Receiver

Control Box with Battery

120 Volt Indoor

Transformer

(Surge Protector,

not supplied)

Run up to 1000' of low voltage wire to control box from transformer. (wire not included)

Post Bracket Assembly

 

 

Gate Bracket

 

 

GTO/PRO 2000 – First Operator

GTO/PRO 2200 – Second Operator

Power Cable

Closed Position Positive Stop Plate

 

PVC conduit (not included) to protect wire from lawnmowers and weedeaters.

The open position stop for

 

 

 

the second gate is installed

Gate Hinge

Ground Stop (under gate)

Gate Hinge

the same as the first gate.

 

 

 

See instructions on page 16.

 

 

 

The Closed position stops

 

 

 

on a dual gate system

 

Closed Position

 

require a ground stop for

 

Stop Plates

 

the second gate (first to

 

 

 

close) to be installed as

 

Not to exceed 110°

Not to exceed 110°

follows:

 

 

 

Step D1:

 

Wood, metal, or concrete

 

 

post set in concrete.

 

Open Position Stop

Open Position Stop

Attach the closed position

 

 

 

stop plate vertically to the

 

 

 

inside bottom of the gate

 

 

 

that will receive the

 

 

 

second operator (for push-

 

 

 

to-open, install plate on

 

 

 

outside of gate). In this

 

Closed Position Stop Plate mounted

illustration this is the gate

 

 

on second gate (first gate to close).

that will close first.

 

 

 

 

 

 

 

SIDE VIEW

 

Closed position stop plate

StepD2:

Low profile ground stop

Install a closed position ground stop in driveway securely

in middle of driveway

FRONT VIEW

into ground directly below the gate. The positive stop

 

plate installed in Step D1 should rest against the ground

 

stop in the closed position. For added security, install a

 

GTO Automatic Gate Lock (see Accessory Catalog).

 

38

Image 41
Contents Series Converting Temperature Table of Contents Disconnecting the Operator Important Safety InstructionsII. During Installation Before InstallationIII. After Installation Secondary Means of Protection Against Entrapment Entrapment Alarm UL 325 30A.1.1ANo ONE should Cross the Path of the Moving Gate Consumer/End UserEntrapment Protection Required Safety Precautions for Swing GatesInstall Warning Signs Moving Gate Can Cause Injury Or Death GTO/PRO 2000 Series Swing Gate Operators Technical SpecificationsHardware not to scale PartsControl Box and Electrical Components Single Gate Operator Parts ListStep Preparing the GatePull-to-Open Single Gate gate opens into the property Installing The Post Bracket Assembly Step 1/ nut. Note when tightening Connecting Operator to Post Bracket AssemblyRear mount bolt, leave it loose Enough for the operator to pivotInstalling the Gate Bracket Installing the Open and Closed Position Stops Mounting the Control Box Battery Never insert the battery with the terminals to the rightGate Length Powering the SystemEstimated Maximum Number of Cycles Per Day Splice wires togetherSolar Zones and Gate Activity Not touch each other Make sure the exposed wires do not touch each otherDIP Switches Control Board SettingsPotentiometers Remove the Transmitter Cover Setting the Personal Transmitter CodeSet the transmitter DIP Switches Run the cable through PVC conduit to protect it from damage Mounting the ReceiverMemory For Push-to-Open Installations Setting the Closed Position Limit SwitchStep For Pull-to-Open Installations Step Connecting Additional Safety Devices Photoelectric Beams Compatible Safety DevicesSafety Edges WHT white used with GRN green Connecting AccessoriesBLU blue used with GRN green ORG orange used with GRN greenStep PTO-2 Push-to-Open InstallationStep PTO-1 Step PTO-4 Step PTO-3Step PTO-5 Step PTO-6Maintenance Maintenance and Troubleshooting GuidePage GTO, Inc., 3121 Hartsfield Road, Tallahassee, Florida, USA Warranty and Repair ServiceLimited Two Year Warranty Column Installation Information GTO/PRO 2200 Dual Gate System Second Unit Parts ListGTO Automatic Gate Lock see Accessory Catalog Installing The Second UnitStep D1 StepD2StepD3 Connecting the Second Operator to the Control BoardStep D-4 Step D-5Step D-7 Setting the Control Board for Dual Gate InstallationsStep D-8 Step D-9Step D-11 GTO Nema Box FM317 Accessories Available Through Your DealerRB101 433IH ACCESS-oriesRB509 Master Pin Lock RB975Replacement Batteries Access -oriesInstallation of this operator conforms to Class Installation Check list