Step D-7:

Cut slot into driveway and lay the 25 foot power cable for the second operator in this slot (see Illustration on page 38).

NOTE: DO NOT attempt to splice the power cable, and DO NOT remove the connector from the end of the cable.

If you need a longer cable, 35 foot and 40 foot power cables are available (see Accessory Catalog).

Setting the Control Board for Dual Gate Installations

DIP Switches

The Control Board DIP switches must be set to accommodate your particular type of installation. Since the

SNGL / DUAL, SEQ1, and SEQ2 DIP switches are used by dual gate operator systems, they will be discussed in the following steps.

Step D-8:

Make sure the control box power switch is OFF.

Step D-9:

Unscrew and remove the control box cover. Use a small screwdriver to move the SNGL / DUAL DIP switch to DUAL (see illustration).

The order of gate operation ("sequencing") must now be determined for your dual gate operators to function properly.

Refer to the illustrations on the next page.

NOTE: The terms "FIRST OPERATOR" and "SECOND OPERATOR" refer to a unit wired to the terminal block of the same name.

Step D-10:

￿

PULL/PUSH

￿

SNGL/DUAL

￿

SEQ1

￿

￿￿SEQ2

OBSTRUCT

SENS.

MIN MAX

LEARN

BOTH OPERATORS OPEN SIMULTANEOUSLY BOTH OPERATORS CLOSE SIMULTANEOUSLY

SEQ1 = ON SEQ2 = OFF

If SEQ1 is set to ON, and SEQ2 is set to OFF, the FIRST OPERATOR and SECOND OPERATOR open simultaneously (see illustration), and the FIRST OPERA- TOR and SECOND OPERATOR close simultaneously.

￿

PULL/PUSH

￿

SNGL/DUAL

￿

SEQ1

￿￿SEQ2￿

OBSTRUCT

SENS.

MIN MAX

LEARN

40

Image 43
Contents Series Converting Temperature Table of Contents Disconnecting the Operator Important Safety InstructionsII. During Installation Before InstallationIII. After Installation Secondary Means of Protection Against Entrapment Entrapment Alarm UL 325 30A.1.1ANo ONE should Cross the Path of the Moving Gate Consumer/End UserInstall Warning Signs Required Safety Precautions for Swing GatesEntrapment Protection Moving Gate Can Cause Injury Or Death GTO/PRO 2000 Series Swing Gate Operators Technical SpecificationsHardware not to scale PartsControl Box and Electrical Components Single Gate Operator Parts ListPull-to-Open Single Gate gate opens into the property Preparing the GateStep Installing The Post Bracket Assembly Step Enough for the operator to pivot Connecting Operator to Post Bracket Assembly1/ nut. Note when tightening Rear mount bolt, leave it looseInstalling the Gate Bracket Installing the Open and Closed Position Stops Mounting the Control Box Battery Never insert the battery with the terminals to the rightGate Length Powering the SystemSolar Zones and Gate Activity Splice wires togetherEstimated Maximum Number of Cycles Per Day Not touch each other Make sure the exposed wires do not touch each otherDIP Switches Control Board SettingsPotentiometers Set the transmitter DIP Switches Setting the Personal Transmitter CodeRemove the Transmitter Cover Memory Mounting the ReceiverRun the cable through PVC conduit to protect it from damage Step For Pull-to-Open Installations Setting the Closed Position Limit SwitchFor Push-to-Open Installations Step Connecting Additional Safety Devices Safety Edges Compatible Safety DevicesPhotoelectric Beams ORG orange used with GRN green Connecting AccessoriesWHT white used with GRN green BLU blue used with GRN greenStep PTO-1 Push-to-Open InstallationStep PTO-2 Step PTO-6 Step PTO-3Step PTO-4 Step PTO-5Maintenance Maintenance and Troubleshooting GuidePage Limited Two Year Warranty Warranty and Repair ServiceGTO, Inc., 3121 Hartsfield Road, Tallahassee, Florida, USA Column Installation Information GTO/PRO 2200 Dual Gate System Second Unit Parts ListStepD2 Installing The Second UnitGTO Automatic Gate Lock see Accessory Catalog Step D1Step D-5 Connecting the Second Operator to the Control BoardStepD3 Step D-4Step D-9 Setting the Control Board for Dual Gate InstallationsStep D-7 Step D-8Step D-11 RB101 Accessories Available Through Your DealerGTO Nema Box FM317 Master Pin Lock RB975 ACCESS-ories433IH RB509Replacement Batteries Access -oriesInstallation of this operator conforms to Class Installation Check list