GTO RB923 rev Installation Check list, Installation of this operator conforms to Class

Page 48

Installation Check list

The installation of this operator conforms to CLASS __________.

The installer verifies that (each item except safety edges must be checked):

____ Recommended safety edges were installed.

____ Customer was informed that this gate is for vehicular use ONLY. Pedestrians MAY NOT use this gate.

____ A separate gate or entrance was installed for pedestrian use.

____ Closed position stop plate was securely fastened.

____ All power cables, receiver cables, and transformer plugs were securely fastened.

____ Petroleum jelly was applied to the control board terminals.

____ All warning signs and labels were installed as specified in the IMPORTANT SAFETY INSTRUCTIONS.

____ The IMPORTANT SAFETY INSTRUCTIONS were reviewed with the customer.

____ The Installation Manual was given to the customer.

____ The customer was instructed to use silicone spray on the push/pull tube, front mount, and rear mount to maintain the

gate operator.

____ Customer was instructed about disconnecting the operator for manual operation of the gate

____ Customer was instructed about proper use of transmitter and (or) other entry controls.

____ Customer was asked to fill out customer support card and mail it to GTO, Inc.

____ Customer was asked to retain all receipts (receipts provide proof of warranty).

____ The completed installation was photographed from both the front and back of the gate. Photo was dated.

Customer’s Signature

Date

Installer’s Signature

Date

45

Image 48
Contents Series Converting Temperature Table of Contents Important Safety Instructions Disconnecting the OperatorBefore Installation II. During InstallationIII. After Installation Entrapment Alarm UL 325 30A.1.1A Secondary Means of Protection Against EntrapmentConsumer/End User No ONE should Cross the Path of the Moving GateRequired Safety Precautions for Swing Gates Install Warning SignsEntrapment Protection Moving Gate Can Cause Injury Or Death Technical Specifications GTO/PRO 2000 Series Swing Gate OperatorsParts Hardware not to scaleSingle Gate Operator Parts List Control Box and Electrical ComponentsPreparing the Gate Pull-to-Open Single Gate gate opens into the propertyStep Installing The Post Bracket Assembly Step Connecting Operator to Post Bracket Assembly 1/ nut. Note when tighteningRear mount bolt, leave it loose Enough for the operator to pivotInstalling the Gate Bracket Installing the Open and Closed Position Stops Mounting the Control Box Never insert the battery with the terminals to the right BatteryPowering the System Gate LengthSplice wires together Solar Zones and Gate ActivityEstimated Maximum Number of Cycles Per Day Make sure the exposed wires do not touch each other Not touch each otherControl Board Settings DIP SwitchesPotentiometers Setting the Personal Transmitter Code Set the transmitter DIP SwitchesRemove the Transmitter Cover Mounting the Receiver MemoryRun the cable through PVC conduit to protect it from damage Setting the Closed Position Limit Switch Step For Pull-to-Open InstallationsFor Push-to-Open Installations Step Connecting Additional Safety Devices Compatible Safety Devices Safety EdgesPhotoelectric Beams Connecting Accessories WHT white used with GRN greenBLU blue used with GRN green ORG orange used with GRN greenPush-to-Open Installation Step PTO-1Step PTO-2 Step PTO-3 Step PTO-4Step PTO-5 Step PTO-6Maintenance and Troubleshooting Guide MaintenancePage Warranty and Repair Service Limited Two Year WarrantyGTO, Inc., 3121 Hartsfield Road, Tallahassee, Florida, USA Column Installation Information Second Unit Parts List GTO/PRO 2200 Dual Gate SystemInstalling The Second Unit GTO Automatic Gate Lock see Accessory CatalogStep D1 StepD2Connecting the Second Operator to the Control Board StepD3Step D-4 Step D-5Setting the Control Board for Dual Gate Installations Step D-7Step D-8 Step D-9Step D-11 Accessories Available Through Your Dealer RB101GTO Nema Box FM317 ACCESS-ories 433IHRB509 Master Pin Lock RB975Access -ories Replacement BatteriesInstallation Check list Installation of this operator conforms to Class