Item | Area/condition | Yes | No | Comment/date |
|
|
|
|
|
6 | Is there a dedicated branch circuit for equipment? |
|
|
|
|
|
|
|
|
7 | Is there a dedicated branch circuit less than 22.86 m (75 ft) away? |
|
|
|
|
|
|
|
|
8 | Are the input circuit breakers sized to protect their respective |
|
|
|
| receptacles for equipment loads? |
|
|
|
Safety considerations
Item | Area/condition | Yes | No | Comment/date |
|
|
|
|
|
1 | Is there an emergency power shutoff switch? |
|
|
|
|
|
|
|
|
2 | Is there a telephone available for emergency purposes? |
|
|
|
|
|
|
|
|
3 | Is there a fire protection system in the computer room? |
|
|
|
|
|
|
|
|
4 | Is antistatic flooring installed? |
|
|
|
|
|
|
|
|
Cooling considerations
Item | Area/condition | Yes | No | Comment/date |
|
|
|
|
|
1 | Can the room temperature be maintained between the recommended |
|
|
|
| range of 20°C to 25°C (68°F to 77°F) and allowable range of 15°C |
|
|
|
| to 32°C (59°F to 90°F) (up to 5,000 ft)? Derate 1°C/1,000 ft above |
|
|
|
| 5,000 ft and up to 10,000 ft. |
|
|
|
2 | Can the humidity level be maintained at the recommended level of |
|
|
|
| 40% to 50%, with allowable humidity levels of 20% to 60%? |
|
|
|
3 | Are air conditioning filters installed and clean? |
|
|
|
|
|
|
|
|
Water preparation considerations
Item | Area/condition | Yes | No | Comment/date |
|
|
|
|
|
|
|
1 | Has the water been tested for acceptable quality for use in the HP |
|
|
|
|
| Modular Cooling System 200/100? |
|
|
|
|
2 | If the water quality is unacceptable, have adequate treatment |
|
|
|
|
| filtration measures been put in place? |
|
|
|
|
3 | Have the water temperature and flow been evaluated? |
|
|
|
|
|
|
|
|
|
|
4 | Has piping of an appropriate diameter, material, and pressure |
|
|
|
|
| tolerance been installed to reach the back of each |
|
|
|
|
|
|
|
|
| |
5 | Is there a provision for fluid collected from the condensation and |
|
|
|
|
| overflow hoses at each |
|
|
|
|
6 | Is there dedicated cabinet space for storage of water quality |
|
|
|
|
| chemicals and gloves? |
|
|
|
|
7 | Is there an available space to prepare and handle chemicals before |
|
|
|
|
| adding them to the system? |
|
|
|
|
8 | Is Nalprep 8349 (commercially available from Nalco Company) |
|
|
|
|
| available on site for the secondary loop cleaning procedure? |
|
|
|
|
9 | Has the approximate volume of water in the entire system been |
|
|
|
|
| determined? (Necessary for water chemical preparation) |
|
|
|
|
10 | Have the water treatment chemicals been evaluated and approved |
|
|
|
|
| through your facility EHS department? |
|
|
|
|
|