HP Modular Cooling System Physical specifications, MCS-100 expansion rack physical specifications

Page 17

For easier viewing, the canopies are not shown in this illustration.

Item

Reference

 

 

1

Water module

2

Fan module

3

Condensation pump transformer 277v (optional)

4

AC transfer switch

5

Emergency door opening

Physical specifications

The following table lists the approximate physical specifications of a single MCS-100 or MCS-200 as received from the factory.

MCS-100 (single rack configuration) physical specifications

Parameter

Packaged system (as

Unpackaged system

Unpackaged CTO system

 

shipped on pallet)

(off pallet, unwrapped)

 

 

 

 

 

Height

2285 mm (90 inches)

2007 mm (79 inches)

2007 mm (79 inches)

Width

1219 mm (48 inches)

904 mm (35.6 inches)

904 mm (35.6 inches)

 

 

 

 

Depth

1829 mm (72 inches)

1311 mm (51.6 inches)

1311 mm (51.6 inches)

Weight

670 kg (1479 lb)1

417 kg (919 lb)2

1324 kg (2919 lb)3

MCS-100 expansion rack physical specifications

Overview 17

Image 17
Contents Part Number June Edition HP Modular Cooling System 200/100 Site Preparation GuidePage Contents Before you contact HP HP contact information Appendix B Conversion factors and formulasOverview OverviewMCS-100 unit dual-rack configuration MCS-200 unit single-rack configuration Product overview Air flow for MCS-100 single-rack configuration Air flow for MCS-100 dual-rack configuration Air flow for MCS-200 single-rack configuration Key components MCS-100 components Description MCS-200 components Unit top view MCS-100 expansion rack physical specifications Physical specificationsElectrical specifications Parameter Value Comments Space and positioning considerations Facility planning for implementationFacility planning overview Maneuvering space requirements Delivery space requirementsMCS-200/100 Reference MCS-200/100 expansion rack Reference Operational space requirementsFacility planning for implementation System positioning Cable openings Facility planning for implementation Facility planning for implementation Top view Bottom view Cabinet leveling feetFacility planning for implementation MCS-100 dual-rack configuration IT rack side view MCS-100 single-rack configuration Facility planning for implementation MCS-200 single-rack configuration MCS-200 dual-rack configuration IT rack side view MCS-200 single-rack configuration Floor loading considerations Facility planning for implementation Page Electrical considerations WeightTerm Description RatingSystem grounding MCS-200 Raised floor grounding Description Electrical planning around water-handling components Connecting to facility A/C powerVoltage fluctuations and outages Facility planning for implementation Coolant source planning Plumbing considerations HP Water Hook-Up Kit M6 screw Above the floor for MCS-200 only Facility planning for implementation Piping approaches Hose openings Bottom view Top view MCS-200 hose openings Bottom view Top view MCS-100 floor tile cutouts Raised floor cutouts for the MCS unitRear view Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Chilled water system components Fittings Astm B16.22 Wrought copper Strainer Description SpecificationsWatts TP or equivalent Typical plumbing installation guidelinesGeneral thermal requirements Coolant requirementsDetermining heat load capacities Cooling loop sizingPage Facility planning for implementation Facility planning for implementation Facility planning for implementation Facility planning for implementation Additional water precautions Acceptable water quality specificationsEnvironmental considerations Before installing and running active componentsControl system Plumbing materials to avoidFacility planning for implementation Delivery survey form Appendix a Forms and checklistsDimension Measurement Area/condition Yes Comment/date Pre-installation checklistsSite preparation checklist Safety considerations Appendix a Forms and checklists Conversion factors and formulas Appendix B Conversion factors and formulasRegulatory information Safety and regulatory complianceWarranty information Regulatory requirements for Exit signs Regulatory information HP contact information Support and other resourcesBefore you contact HP Acronyms and abbreviations Water steam pressure Uninterruptible power systemDocumentation feedback Index Site preparation checklist