D. Mantel and Wall Projections

WARNING! Risk of Fire! Comply with all minimum clear- ances as specified. Framing or finishing material closer than the minimums listed must be constructed entirely of non- combustible materials (i.e., steel studs, concrete board, etc). Failure to comply could cause fire.

Combustible Mantels

12 IN.

MAX.

10 IN.

MIN.

FIREPLACE

OPENING

Figure 5.3 Clearances to mantels or other combustibles above appliance

Non-combustible Mantels

12 IN. MAX.

10 IN.

MIN.

4 IN.

MAX.

NON-COMBUSTIBLE MATERIAL

FIREPLACE

OPENING

Figure 5.4 Clearances to Mantels or other Non-Combustibles Above Appliance

Combustible Mantel Legs or Wall Projections

FIREPLACE

1 IN. MIN.

OPENING

 

 

COMBUSTIBLE

 

MATERIAL

 

6 IN.

 

MAX.

 

7 IN.

 

6 IN. MIN. FROM

 

OPENING

 

13 IN. MIN.

 

FROM OPENING

 

COMBUSTIBLE WALL OR

 

MANTEL LEG

Figure 5.5 Clearances to Combustible Mantel Legs or Wall Projections.

Non-Combustible Mantel Legs or Wall Projections

FIREPLACE

 

OPENING

1 IN. MIN.

4 IN. MAX.

NON-COMBUSTIBLE

 

MANTEL LEG

 

13 IN. MIN.

 

NON-COMBUSTIBLE WALL

Figure 5.6 Clearances to Non-Combustible Mantel Legs or Wall Projections.

Heat & Glo • ESC-42ST2146-900 Rev. o • 5/12

21

Image 21
Contents Model ESC-42ST What to do if you smell gasDo Discardnot Homeowner Reference Information CongratulationsUser Guide Table of ContentsAppliance Setup TroubleshootingReference Materials Limited Lifetime Warranty Warranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Remote Control Fixed Glass AssemblyClear Space Decorative Doors and FrontsModule Reset IPI Battery Tray/Battery InstallationNine Hour Safety Shutdown Feature Control Module OperationFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsMaintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Exterior of Installed Glass Only Doors, Surrounds, FrontsGlass Cleaning Exterior and Interior of Installed Glass Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsFrequency As needed Light Bulb MaintenanceTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Framing and Clearances Selecting Appliance LocationBoard not Shown Attached to Minimum Framing Dimensions Constructing the Appliance ChaseClearances MIN MAX NON-COMBUSTIBLE Material Fireplace Opening Mantel and Wall ProjectionsCombustible Material Hearth ExtensionVent Termination Minimum Clearances Termination LocationsInches U.S.A Covered Alcove ApplicationsApproved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsVent Diagrams Top Vent Horizontal Termination One Elbow Top Vent Horizontal TerminationTwo Elbows H1+ H2Top Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Ht Max Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Non-Combustible Wall PenetrationPipe DVP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationAppliance Package Identification Securing and Leveling the ApplianceAttach Vent to the Firebox Assembly Installing Vent PipeAssemble Vent Sections Assemble Pipe SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Horizontal Termination CapHeat Shield Requirements for Horizontal Termination Fuel Conversion Gas InformationGas Pressure Gas ConnectionIntelliFire Plus Ignition System Wiring Wiring RequirementsElectrical Service and Repair Junction Box Installation Electrical InformationIPI Wiring Diagram Finishing Doors Facing MaterialModel Description Elevated Appliance Dimension Elevated Hearth SystemsESC-42ST TAB Appliance SetupAccessories Clean the ApplianceInstalling the Optional Heat-ZoneGas Kit Remove the Shipping MaterialsEmber Lights Install Light BulbsAccent Lights ScrewsNotch Install RefractoryFlange Outer Firebox Flange Refractory ClipsMystic Ember Placement Install Teco-Sil Glass Ember RockLOG Placement Instructions Grate Tine Grate BAR 4 Install Outer Refractory Panels Ember/Mineral Wool PlacementInstall Trim and/or Surround Install MeshAir Shutter Setting Air Shutter SettingsTroubleshooting Symptom Possible Cause Corrective ActionIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP-TRAP DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2RF6M RF12M Description Part Number Optional Wire HarnessService Parts Refractory Assembly Log Set AssemblyService Parts List At DepotDescription Comments Part Number Stocked Pre SN#28 IPI Valve Assembly Post SN Contact Information