E. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.15

F. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.18).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

Heat & Glo • ESC-42ST2146-900 Rev. o • 5/12

39

Image 39
Contents Model ESC-42ST What to do if you smell gasDo Discardnot Homeowner Reference Information CongratulationsUser Guide Table of ContentsAppliance Setup TroubleshootingReference Materials Limited Lifetime Warranty Warranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Decorative Doors and Fronts Fixed Glass AssemblyRemote Control Clear SpaceControl Module Operation IPI Battery Tray/Battery InstallationModule Reset Nine Hour Safety Shutdown FeatureFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsDoors, Surrounds, Fronts Maintenance and ServiceMaintenance Tasks-Homeowner Glass Cleaning Exterior of Installed Glass OnlyLogs Maintenance Tasks-Qualified Service TechnicianGlass Cleaning Exterior and Interior of Installed Glass Gasket Seal and Glass Assembly InspectionFrequency As needed Light Bulb MaintenanceTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Framing and Clearances Selecting Appliance LocationBoard not Shown Attached to Minimum Framing Dimensions Constructing the Appliance ChaseClearances MIN MAX NON-COMBUSTIBLE Material Fireplace Opening Mantel and Wall ProjectionsCombustible Material Hearth ExtensionVent Termination Minimum Clearances Termination LocationsInches U.S.A Covered Alcove ApplicationsUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyVent Diagrams H1+ H2 Top Vent Horizontal TerminationTop Vent Horizontal Termination One Elbow Two ElbowsTop Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Ht Max Non-Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationAppliance Package Identification Securing and Leveling the ApplianceAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Horizontal Termination CapHeat Shield Requirements for Horizontal Termination Gas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntelliFire Plus Ignition System Wiring Electrical Service and Repair Junction Box InstallationIPI Wiring Diagram Finishing Doors Facing MaterialModel Description Elevated Appliance Dimension Elevated Hearth SystemsESC-42ST TAB Appliance SetupRemove the Shipping Materials Clean the ApplianceAccessories Installing the Optional Heat-ZoneGas KitScrews Install Light BulbsEmber Lights Accent LightsOuter Firebox Flange Refractory Clips Install RefractoryNotch FlangeMystic Ember Placement Install Teco-Sil Glass Ember RockLOG Placement Instructions Grate Tine Grate BAR 4 Install Outer Refractory Panels Ember/Mineral Wool PlacementAir Shutter Settings Install MeshInstall Trim and/or Surround Air Shutter SettingTroubleshooting Symptom Possible Cause Corrective ActionIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP-TRAP DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2RF6M RF12M Description Part Number Optional Wire HarnessService Parts Refractory Assembly Log Set AssemblyService Parts List At DepotDescription Comments Part Number Stocked Pre SN#28 IPI Valve Assembly Post SN Contact Information