G. Install Refractory

CAUTION: Refractory pieces are fragile! Carefully remove the refractory pieces from the packaging.

1.Locate the four refractory clips pre-installed in the top of the firebox and remove. Install side refractory with the notched end of the refractory on the bottom. See Figure 14.14 and Figure 14.15. Ensure that side refractory panels are centered left and right and do not extend past the outer firebox flange. Secure each side refractory with two refractory clips.

NOTCH

Figure 14.14 Notched End of Side Refractory

2.Install the left and right refractory middle base refractory pieces on top of the left and right bottom refractory standoffs. See Figure 14.16 and 14.17. Position so that the edge is flush with the ember light housing.

Figure 14.16 Positioning Inner Bottom Refractory

FLANGE

Figure 14.17 Positioning Left and Right Middle Base Refractory

OUTER FIREBOX

FLANGE

REFRACTORY

CLIPS

Figure 14.15 Refractory Clip Installation

Figure 14.18 Positioning Outer Bottom Refractory.

5. Install two outer bottom refractory pieces as shown in Figure 14.18. Ensure that outer bottom refractory pieces do not extend past the outer firebox flange.

50

Heat & Glo • ESC-42ST2146-900 Rev. o • 5/12

Image 50
Contents Do Discardnot Model ESC-42STWhat to do if you smell gas Congratulations Homeowner Reference InformationTable of Contents User GuideReference Materials Appliance SetupTroubleshooting Limited Lifetime Warranty Limited Lifetime Warranty Warranty ConditionsListing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Clear Space Fixed Glass AssemblyRemote Control Decorative Doors and FrontsNine Hour Safety Shutdown Feature IPI Battery Tray/Battery InstallationModule Reset Control Module OperationLighting Instructions IPI Final inspection byFrequently Asked Questions After Fireplace is LitGlass Cleaning Exterior of Installed Glass Only Maintenance and ServiceMaintenance Tasks-Homeowner Doors, Surrounds, FrontsGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianGlass Cleaning Exterior and Interior of Installed Glass LogsLight Bulb Maintenance Frequency As neededGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Board not Shown Attached to Framing and ClearancesSelecting Appliance Location Clearances Minimum Framing DimensionsConstructing the Appliance Chase Mantel and Wall Projections MIN MAX NON-COMBUSTIBLE Material Fireplace OpeningHearth Extension Combustible MaterialTermination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Inches U.S.AVent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsVent Diagrams Two Elbows Top Vent Horizontal TerminationTop Vent Horizontal Termination One Elbow H1+ H2Top Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Ht Max Wall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Non-Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Top VentSecuring and Leveling the Appliance Appliance Package IdentificationAssemble Vent Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Slip Sections Secure the Vent Sections10 Rotate Seams for Disassembly Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Horizontal Termination Cap Gas Pressure Gas InformationFuel Conversion Gas ConnectionElectrical Service and Repair Junction Box Installation Wiring RequirementsIntelliFire Plus Ignition System Wiring Electrical InformationIPI Wiring Diagram Finishing Facing Material DoorsESC-42ST Model Description Elevated Appliance DimensionElevated Hearth Systems Appliance Setup TABInstalling the Optional Heat-ZoneGas Kit Clean the ApplianceAccessories Remove the Shipping MaterialsAccent Lights Install Light BulbsEmber Lights ScrewsFlange Install RefractoryNotch Outer Firebox Flange Refractory ClipsInstall Teco-Sil Glass Ember Rock Mystic Ember PlacementLOG Placement Instructions Grate BAR Grate Tine 4 Ember/Mineral Wool Placement Install Outer Refractory PanelsAir Shutter Setting Install MeshInstall Trim and/or Surround Air Shutter SettingsIntelliFire Plus Ignition System TroubleshootingSymptom Possible Cause Corrective Action Troubleshooting Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP-AS2DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2 DVP-TRAPRF6M RF12M Optional Wire Harness Description Part NumberRefractory Assembly Log Set Assembly Service PartsDescription Comments Part Number Service Parts ListAt Depot Pre SN Stocked#28 IPI Valve Assembly Post SN Contact Information