Heat & Glo LifeStyle ESC-42ST Vent Clearances and Framing, Pipe Clearances to Combustibles

Page 31

8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184 mm) thick.

If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If wall thickness is greater than 7-1/4 in. a DVP-HSM-B will be required.

If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed. If wall thickness is greater than 7-5/8 in. a DVP-HSM-B will be required.

DVP pipe - A wall shield firestop is required on one side only on interior walls. If your local inspector requires a wall shield firestop on both sides, then both wall shield firestops must have a heat shield (refer to Section 16.B.) attached to them.

See Section 10.J. for information for regarding the in- stallation of a horizontal termination cap.

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncom- bustible materials such as concrete, a hole with diameter one inch greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

(DVP Pipe Shown)

 

 

Heat

 

3 in. (76 mm)

Shield

 

 

 

top clearance

 

1 in. (25 mm)

1 in. (25 mm)

clearance

 

clearance around

 

bottom & sides

vertical sections

 

 

 

 

Wall

 

 

Shield

 

 

Firestop

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

B

A*

WALL

Figure 8.1 Horizontal Venting Clearances To Combustible Materials

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield firestop must be placed on each side of an interior wall. A minimum 1-1/2 in. (38 mm) overlap of attached heat shields must be maintained.

DO NOT PACK WITH INSULATION

OR OTHER MATERIAL

A*

 

A*

B

Inches

75

74

Millimeters

1905

1880

*Shows center of vent framing hole for top or rear venting. The center of the hole is one (1) in. (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.2 Wall Penetration

Heat & Glo • ESC-42ST2146-900 Rev. o • 5/12

31

Image 31
Contents What to do if you smell gas Model ESC-42STDo Discardnot Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupReference Materials Limited Lifetime Warranty Warranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Decorative Doors and Fronts Fixed Glass AssemblyRemote Control Clear SpaceControl Module Operation IPI Battery Tray/Battery InstallationModule Reset Nine Hour Safety Shutdown FeatureFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsDoors, Surrounds, Fronts Maintenance and ServiceMaintenance Tasks-Homeowner Glass Cleaning Exterior of Installed Glass OnlyLogs Maintenance Tasks-Qualified Service TechnicianGlass Cleaning Exterior and Interior of Installed Glass Gasket Seal and Glass Assembly InspectionFrequency As needed Light Bulb MaintenanceTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesBoard not Shown Attached to Constructing the Appliance Chase Minimum Framing DimensionsClearances MIN MAX NON-COMBUSTIBLE Material Fireplace Opening Mantel and Wall ProjectionsCombustible Material Hearth ExtensionVent Termination Minimum Clearances Termination LocationsInches U.S.A Covered Alcove ApplicationsUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyVent Diagrams H1+ H2 Top Vent Horizontal TerminationTop Vent Horizontal Termination One Elbow Two ElbowsTop Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Ht Max Non-Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Top Vent Appliance PreparationAppliance Package Identification Securing and Leveling the ApplianceAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingInstall Horizontal Termination Cap Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Gas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntelliFire Plus Ignition System Wiring Electrical Service and Repair Junction Box InstallationIPI Wiring Diagram Finishing Doors Facing MaterialElevated Hearth Systems Model Description Elevated Appliance DimensionESC-42ST TAB Appliance SetupRemove the Shipping Materials Clean the ApplianceAccessories Installing the Optional Heat-ZoneGas KitScrews Install Light BulbsEmber Lights Accent LightsOuter Firebox Flange Refractory Clips Install RefractoryNotch FlangeMystic Ember Placement Install Teco-Sil Glass Ember RockLOG Placement Instructions Grate Tine Grate BAR 4 Install Outer Refractory Panels Ember/Mineral Wool PlacementAir Shutter Settings Install MeshInstall Trim and/or Surround Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP-TRAP DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2RF6M RF12M Description Part Number Optional Wire HarnessService Parts Refractory Assembly Log Set AssemblyAt Depot Service Parts ListDescription Comments Part Number Stocked Pre SN#28 IPI Valve Assembly Post SN Contact Information