K. Ember/Mineral Wool Placement

WARNING! Risk of Explosion! DO NOT place embers directly over burner ports. Improperly placed embers inter- fere with proper burner operation. See instructions.

Ember material is shipped with this gas appliance. To place the ember material:

Place dime-size pieces of Glowing Embers® just in front of the port trail, but not on or in between the ports See Figure 14.23. Embers are to be placed adjacent to burner port holes. Care should be taken so that the ports are not covered. Failure to follow this procedure will likely cause lighting and sooting problems.

Embers CANNOT be placed directly over ports. Care should be taken not to cover the lighting trail of ports (from back to front).

NO EMBERS IN THIS AREA

Figure 14.23 Ember Placement

L. Install Outer Refractory Panels

1.Install glass assembly. Refer to Section 14.A for glass installation.

2.The refractory brackets are shipped wire-tied to the right side support opposite the valve. See Figure 14.24. Bend the back support of the refractory tab down. See Figure 14.25. Install the two refractory brackets to the glass frame and secure, but do not tighten. One screw per bracket is required. See Figure 14.26.

3.Install both outer refractory panels and install refrac- tory bracket to secure refractory panels in place. See Figure 14.26.

4.Install Outer Hearth. See Figure 14.27.

Figure 14.24 Shipping Location of Refractory Brackets

BACK SUPPORT

TAB

Figure 14.25 Back Support Tab Bent Into Position

Figure 14.26 Side Refractory Brackets

Figure 14.27 Outer Hearth Installation

Heat & Glo • ESC-42ST2146-900 Rev. o • 5/12

55

Image 55
Contents What to do if you smell gas Model ESC-42STDo Discardnot Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupReference Materials Limited Lifetime Warranty Warranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Decorative Doors and Fronts Fixed Glass AssemblyRemote Control Clear SpaceControl Module Operation IPI Battery Tray/Battery InstallationModule Reset Nine Hour Safety Shutdown FeatureFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsDoors, Surrounds, Fronts Maintenance and ServiceMaintenance Tasks-Homeowner Glass Cleaning Exterior of Installed Glass OnlyLogs Maintenance Tasks-Qualified Service TechnicianGlass Cleaning Exterior and Interior of Installed Glass Gasket Seal and Glass Assembly InspectionFrequency As needed Light Bulb MaintenanceTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesBoard not Shown Attached to Constructing the Appliance Chase Minimum Framing DimensionsClearances MIN MAX NON-COMBUSTIBLE Material Fireplace Opening Mantel and Wall ProjectionsCombustible Material Hearth ExtensionVent Termination Minimum Clearances Termination LocationsInches U.S.A Covered Alcove ApplicationsUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyVent Diagrams H1+ H2 Top Vent Horizontal TerminationTop Vent Horizontal Termination One Elbow Two ElbowsTop Vent Horizontal Termination Three Elbows 12 ft V1 + V2 + H1 = 50 ft 15.2 m Max Ht Max Non-Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Top Vent Appliance PreparationAppliance Package Identification Securing and Leveling the ApplianceAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingInstall Horizontal Termination Cap Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Gas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntelliFire Plus Ignition System Wiring Electrical Service and Repair Junction Box InstallationIPI Wiring Diagram Finishing Doors Facing MaterialElevated Hearth Systems Model Description Elevated Appliance DimensionESC-42ST TAB Appliance SetupRemove the Shipping Materials Clean the ApplianceAccessories Installing the Optional Heat-ZoneGas KitScrews Install Light BulbsEmber Lights Accent LightsOuter Firebox Flange Refractory Clips Install RefractoryNotch FlangeMystic Ember Placement Install Teco-Sil Glass Ember RockLOG Placement Instructions Grate Tine Grate BAR 4 Install Outer Refractory Panels Ember/Mineral Wool PlacementAir Shutter Settings Install MeshInstall Trim and/or Surround Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Troubleshooting Reference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP-TRAP DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2RF6M RF12M Description Part Number Optional Wire HarnessService Parts Refractory Assembly Log Set AssemblyAt Depot Service Parts ListDescription Comments Part Number Stocked Pre SN#28 IPI Valve Assembly Post SN Contact Information