FireplaceXtrordinair 36CF installation manual Framing Dimensions 36 CF Pier, Front

Page 12

12

Installation (for qualified installers only)

Framing Dimensions – 36 CF Pier

Minimum 78” Fireplace

Enclosure Height

18-1/4"

Glass

Centerline

56-1/2”

49-3/8”

22-1/2”

Front

Left

Right

Back

 

Vent Clearances:

8-5/8" Diameter vent requires 3-1/2" clearance to

the sides. You may need to notch the framing to accommodate this clearance.

15-5/8"

NOTE: Do not build into this area - it must be left clear to provide adequate clearance for the vent.

Figure 6

© Travis Industries

4090102

100-01212_000

Image 12
Contents CF ST/Pier Gas Fireplace 2Introduction Overview Listing DetailsTable of Contents Safety Precautions Safety WarningsSafety Precautions Features and Specifications Installation OptionsSpecifications DimensionsRecommended Installation Procedure Packing ListAdditional Items Required Massachusetts Requirements Preparing the Fireplace Stand-offs Fireplace Placement Requirements ClearancesRaised Fireplaces Minimum Framing 36 CF ST See Through BackFraming Dimensions 36 CF Pier FrontAttaching Stand-Offs to Framing Required Electrical Connection Battery Pack / Learn Switch Installation Do not route the wires over the top FireplaceSteps for Installing the Battery Box and Learn Switch Installation Warning Remote SynchronizationBattery Installation Remote Synchronization Synchronizing the RemoteGas Line Requirements Gas Line ConnectionGas Inlet Pressure Vent Installation Vent RequirementsApproved Vent Altitude ConsiderationsVent Clearances Vent LocationApproved Vent Configurations Exhaust Restrictor AdjustmentApproved Vent Configuration Rear Vent, Horz. Term 45 Elbow 0feet Max 5feetFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Hearth Requirements Flush HearthHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing Mantel Requirements See ThroughFinalizing the Installation for qualified installers only Steps for Finalizing the InstallationFinalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Glass Frame Glass TrimLog Set Installation Ember PlacementRock Wool Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Power Heat Duct Installation Andiron Installation48Index