FireplaceXtrordinair 36CF Finalizing the Installation for qualified installers only

Page 36

36 Finalizing the Installation (for qualified installers only)

Steps for Finalizing the Installation

WARNING: Prior to removing the glass, shut off gas to the appliance (or remove the batteries from the battery box and shut off electricity to the fireplace). This prevents any chance of accidental burner ignition when accessing the firebox.

1.Remove the glass (see page 38).

NOTE: If using propane (LP) convert the appliance prior to installing the logs (see page 43 for details)..

2.We recommend you purge the gas line at this time (with the glass removed). This allows gas to be detected once it enters the firebox, ensuring gas does not build up.

3.Install the firebacks (see instructions included with firebacks) and logs (see page 39).

4.Turn on the gas to the fireplace. Turn on gas to the heater. Leak test all gas joints.

5.Replace the glass. Start the pilot.

6.Start the main burner. Leak test all gas joints again (the gas control valve and connections are located on the exterior of the fireplace on the left side.

© Travis Industries

4090102

100-01212_000

Image 36
Contents CF ST/Pier Gas Fireplace 2Introduction Overview Listing DetailsTable of Contents Safety Precautions Safety WarningsSafety Precautions Features and Specifications Installation OptionsSpecifications DimensionsRecommended Installation Procedure Packing ListAdditional Items Required Massachusetts Requirements Preparing the Fireplace Stand-offs Fireplace Placement Requirements ClearancesRaised Fireplaces Minimum Framing 36 CF ST See Through BackFraming Dimensions 36 CF Pier FrontAttaching Stand-Offs to Framing Required Electrical Connection Battery Pack / Learn Switch Installation Do not route the wires over the top FireplaceSteps for Installing the Battery Box and Learn Switch Installation Warning Remote SynchronizationBattery Installation Remote Synchronization Synchronizing the RemoteGas Line Requirements Gas Line ConnectionGas Inlet Pressure Vent Installation Vent RequirementsApproved Vent Altitude ConsiderationsVent Clearances Vent LocationApproved Vent Configurations Exhaust Restrictor AdjustmentApproved Vent Configuration Rear Vent, Horz. Term 45 Elbow 0feet Max 5feetFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Hearth Requirements Flush HearthHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing Mantel Requirements See ThroughFinalizing the Installation for qualified installers only Steps for Finalizing the InstallationFinalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Glass Frame Glass TrimLog Set Installation Ember PlacementRock Wool Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Power Heat Duct Installation Andiron Installation48Index