Installation (for qualified installers only)

Vent Clearances

Vertical Penetrations

(through ceilings, roofs, etc.)

(firestop is required - sku 98900029)

1" Clearance To the Side

IN THE ENCLOSURE (under 78") Vertical or Horizontal Sections:

6" Clearance Above

3-1/2" Clearance To The Side

2" Clearance Below

ABOVE THE ENCLOSURE (over 78")

Vertical Sections:

1" Clearance To the Side

Horizontal Sections:

4" Clearance Above

2" Clearance To The Side 2" Clearance Below

Horizontal Penetrations (through walls, etc.)

(thimble is required - sku 98900030) 4" Clearance Above

2" Clearance To The Side 2" Clearance Below

Vent Location

The starter section is set at a 45° angle. Place a 45° elbow directly on top of the fireplace and route it vertically or horizontally. The approximate position of the vent is shown below.

REAR VENT

TOP VENT

1"

3-1/2"

46"

41-3/4"

Framing to the rear of the fireplace.

NOTE: In cases where the vent is routed vertically directly above the fireplace, you may place a 90° elbow directly on top of the fireplace, followed by a 45° elbow that directs the vent upwards. For vent configuration purposes this is considered a top vent and the 90° and 45° elbow is considered a single 45° elbow.

Framing to the rear of the fireplace.

9-1/4"

56"

© Travis Industries

4090102

100-01212_000

Image 20
Contents CF ST/Pier Gas Fireplace 2Introduction Overview Listing DetailsTable of Contents Safety Precautions Safety WarningsSafety Precautions Features and Specifications Installation OptionsSpecifications DimensionsAdditional Items Required Recommended Installation ProcedurePacking List Massachusetts Requirements Preparing the Fireplace Stand-offs Raised Fireplaces Fireplace Placement RequirementsClearances Minimum Framing 36 CF ST See Through BackFraming Dimensions 36 CF Pier FrontAttaching Stand-Offs to Framing Required Electrical Connection Battery Pack / Learn Switch Installation Do not route the wires over the top FireplaceBattery Installation Steps for Installing the Battery Box and Learn SwitchInstallation Warning Remote Synchronization Remote Synchronization Synchronizing the RemoteGas Inlet Pressure Gas Line RequirementsGas Line Connection Vent Installation Vent RequirementsApproved Vent Altitude ConsiderationsVent Clearances Vent LocationApproved Vent Configurations Exhaust Restrictor AdjustmentApproved Vent Configuration Rear Vent, Horz. Term 45 Elbow 0feet Max 5feetFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Hearth Requirements Flush HearthHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing Mantel Requirements See ThroughFinalizing the Installation for qualified installers only Steps for Finalizing the InstallationFinalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Glass Frame Glass TrimRock Wool Placement Log Set InstallationEmber Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Power Heat Duct Installation Andiron Installation48Index