Installation (for qualified installers only)

Termination Requirements

! Venting terminals shall not be recessed into a wall or siding.

AMinimum 9" clearance from any door or window

BMinimum 12" above any grade, veranda, porch, deck or balcony

CMinimum 3-3/8" from outside corner walls

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

DMinimum 12" from inside corner walls

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

Roof

Surface

11” Min.

6” Min.

Roof Eaves

EMinimum 11" clearance below unventilated soffits or roof surfaces Minimum 18" clearance below ventilated soffits

Minimum 6" clearance below roof eaves NOTE: Vinyl surfaces require 24"

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

FMinimum 12" clearance below a veranda, porch, deck or balcony

NOTE: Permitted only if veranda, porch, deck, or balcony is fully open on a minumum of two sides beneath the floor.

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

GMinimum 48" clearance from any adjacent building

HMinimum 84" clearance above any grade when adjacent to public walkways or driveways NOTE: may not be used over a walkway or driveway shared by an adjacent building

IMinimum 9" clearance to any nonmechanical air supply inlet to the building or the combustion air inlet to any other appliance.

JMinimum 36" clearance above any mechanical air supply inlet if within 10’ horizontally

KMinimum 36" from the area above the meter/regulator (vent outlet)

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

LMinimum 36" from the meter/regulator (vent outlet)

NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

MMinimum 12” above the roof line (for vertical terminations)

NMinimum 24” horizontal clearance to any surface (such as an exterior wall) – for vertical terminations

E

N

M

E

E

A

K J

G A

F

D C I

L

B

NOTE: Measure clearances to the nearest edge of the exhaust hood.

Use the vinyl siding standoff when installing on an exterior with vinyl siding.

Vent termination must not be located where it will become plugged by snow or other material

H

© Travis Industries

4090102

100-01212_000

Image 30
Contents CF ST/Pier Gas Fireplace 2Introduction Overview Listing DetailsTable of Contents Safety Precautions Safety WarningsSafety Precautions Specifications Features and SpecificationsInstallation Options DimensionsRecommended Installation Procedure Packing ListAdditional Items Required Massachusetts Requirements Preparing the Fireplace Stand-offs Fireplace Placement Requirements ClearancesRaised Fireplaces Minimum Framing 36 CF ST See Through BackFraming Dimensions 36 CF Pier FrontAttaching Stand-Offs to Framing Required Electrical Connection Battery Pack / Learn Switch Installation Do not route the wires over the top FireplaceSteps for Installing the Battery Box and Learn Switch Installation Warning Remote SynchronizationBattery Installation Remote Synchronization Synchronizing the RemoteGas Line Requirements Gas Line ConnectionGas Inlet Pressure Approved Vent Vent InstallationVent Requirements Altitude ConsiderationsVent Clearances Vent LocationApproved Vent Configurations Exhaust Restrictor AdjustmentApproved Vent Configuration Rear Vent, Horz. Term 45 Elbow 0feet Max 5feetFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Hearth Requirements Flush HearthHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing Mantel Requirements See ThroughFinalizing the Installation for qualified installers only Steps for Finalizing the InstallationFinalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Glass Frame Glass TrimLog Set Installation Ember PlacementRock Wool Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Power Heat Duct Installation Andiron Installation48Index