FireplaceXtrordinair 36CF installation manual Rate Screws

Page 46

46 Finalizing the Installation (for qualified installers only)

11The gas control valve has a propane conversion shaft that alters the outlet pressure. Remove the rubber cap over the propane conversion shaft and twist the small knob so the line points to “LP” (see Figure 27).

Inlet

Pilot Adj.

Pilot

Outlet

Main

NAT

LP

LP

NAT

Side View

Conversion Shaft

(Note how it is in a lower

 

 

position when switched to LP)

NATURAL TO PROPANE CONVERSION SHAFT (UNDER RUBBER CAP)

NG

LP

(Natural Gas)

(Propane)

Figure 27

12Remove the NG rate screw and replace it with the LP rate screw included in the owner’s pack (see Figure 28). Take care to not damage the rubber o-ring on the rate screw when installing.

Inlet

Pilot Adj.

Pilot

Outlet

Main

NAT

LP

PL

NAT

Rate Screws

RATE SCREW (BRASS)

NGLP

(Natural Gas) (Propane)

Figure 28

13Return the fireplace to the correct configuration (replace firebox and valve cover components).

14The fireplace receiver module will need to be configured for LP. This is done by pressing and holding the “Learn” switch FOR 20 SECONDS (see “Battery Pack / Learn Switch Installation” on page 15). The receiver will give off a short beep (less than 1 second) when configured for LP. The receiver will give off a long beep (3 seconds) when configured for NG. By pressing the switch for 20 seconds, you toggle between the two settings.

15Make the gas line connection, bleed the gas line (if applicable), start the heater and thoroughly leak-test all gas connections and the gas control valve (see Gas Line Requirements on page 18 for details). Check the pilot and adjust if necessary.

© Travis Industries

4090102

100-01212_000

Image 46
Contents CF ST/Pier Gas Fireplace 2Introduction Overview Listing DetailsTable of Contents Safety Precautions Safety WarningsSafety Precautions Specifications Features and SpecificationsInstallation Options DimensionsPacking List Recommended Installation ProcedureAdditional Items Required Massachusetts Requirements Preparing the Fireplace Stand-offs Clearances Fireplace Placement RequirementsRaised Fireplaces Minimum Framing 36 CF ST See Through BackFraming Dimensions 36 CF Pier FrontAttaching Stand-Offs to Framing Required Electrical Connection Battery Pack / Learn Switch Installation Do not route the wires over the top FireplaceInstallation Warning Remote Synchronization Steps for Installing the Battery Box and Learn SwitchBattery Installation Remote Synchronization Synchronizing the RemoteGas Line Connection Gas Line RequirementsGas Inlet Pressure Approved Vent Vent InstallationVent Requirements Altitude ConsiderationsVent Clearances Vent LocationApproved Vent Configurations Exhaust Restrictor AdjustmentApproved Vent Configuration Rear Vent, Horz. Term 45 Elbow 0feet Max 5feetFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Hearth Requirements Flush HearthHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing Mantel Requirements See ThroughFinalizing the Installation for qualified installers only Steps for Finalizing the InstallationFinalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Glass Frame Glass TrimEmber Placement Log Set InstallationRock Wool Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Power Heat Duct Installation Andiron Installation48Index