Installation (for qualified installers only)

7

Packing List

Glass LatchTool

Log Set with Embers and Rock Wool

Remote Control with Wall Mount

LP Conversion Kit (2 orifices and 1 rate screw)

Battery Box

Learn Switch with 12’ Battery Box Wire

Andiron Brackets (4)

Fiber Board

Additional Items Required

Firebacks (SKU 96100177 or 96100178)

1080/36 CF Direct Vent (available only from Travis Industries – see page 19 for part numbers)

Gas Line Equipment (shutoff valve, pipe, etc.)

Electrical Equipment

Recommended Installation Procedure

1.Frame the opening for the fireplace. We suggest omitting the framing above the header to allow for easier vent installation.

2.Place the fireplace in place, making sure it is level and plumb. Attach using the nailing brackets.

3.Install the vent, electrical connection, gas line, and battery box. Install power heat duct (if being used).

4.Install the framing above the header.

5.Install the hearth (if applicable).

6.Install the included non-combustible facing.

7.Install the facing.

8.Install the mantel (if applicable).

9.Finalize the installation (see page 36).

© Travis Industries

4090102

100-01212_000

Image 7
Contents CF ST/Pier Gas Fireplace Overview Listing Details 2IntroductionTable of Contents Safety Warnings Safety PrecautionsSafety Precautions Dimensions Features and SpecificationsInstallation Options SpecificationsPacking List Recommended Installation ProcedureAdditional Items Required Massachusetts Requirements Preparing the Fireplace Stand-offs Clearances Fireplace Placement RequirementsRaised Fireplaces Back Minimum Framing 36 CF ST See ThroughFront Framing Dimensions 36 CF PierAttaching Stand-Offs to Framing Required Electrical Connection Do not route the wires over the top Fireplace Battery Pack / Learn Switch InstallationInstallation Warning Remote Synchronization Steps for Installing the Battery Box and Learn SwitchBattery Installation Synchronizing the Remote Remote SynchronizationGas Line Connection Gas Line RequirementsGas Inlet Pressure Altitude Considerations Vent InstallationVent Requirements Approved VentVent Location Vent ClearancesExhaust Restrictor Adjustment Approved Vent Configurations0feet Max 5feet Approved Vent Configuration Rear Vent, Horz. Term 45 ElbowFeet max 0feet 5feet 10feet 15feet 20max Max 0feet 5feet 10feet 15feet 20max Feet Max Feet max 0feet 5feet 10feet 15feet 20max Installation for qualified installers only 0feet 5feet Feet max 10feet 15feet 40feet max Feet 5feet 10feet 15feet 20max Max 40feet max Feet 5feet 10feet 15feet Termination Requirements Flush Hearth Hearth RequirementsHearth Requirements Recessed Hearth Facing Requirements Non-Combustible Facing See Through Mantel RequirementsSteps for Finalizing the Installation Finalizing the Installation for qualified installers onlyAir Shutter Adjustment Finalizing the Installation for qualified installers onlyGlass Frame Glass Trim Glass Frame Removal and InstallationEmber Placement Log Set InstallationRock Wool Placement Log Installation Top 2 logs last 2 logs Picture from opposite side Picture from end Pier only LP Conversion Instructions Finalizing the Installation for qualified installers only Orifice Table Rate Screws Andiron Installation Power Heat Duct Installation48Index