8 | Installation (for qualified installers only) |
Installation Overview
See "Power Heat Vent" in the optional equipment section.
Drywall
See the section "Vent Requirements"
See the section "Horizontal Termination
Requirements"
See the section "Acceptable
Vent Lengths"
See the section "Mantel Requirements"
See the section "Hearth Requirements"
See the section "Fireplace
Placement Requirements"
Nail
Down
Plate
See the section
"Gas Line Installation"
Insulation must not fill the 1" clearance around the back and sides of the fireplace.
See the section "Electrical Connection"
This grommet and hole is for thermostat wire (on both sides)
See the section "Minimum
Framing Dimensions"
Recommended Installation Procedure
1Frame the opening for the fireplace. Make sure to allow for vent installation and the type of installation (corner or flat wall).
2Insert the fireplace into the framing. Slide it back until the firebox front face is flush with the framing members. Verify all clearances at this point.
3Secure the fireplace to the floor by screwing or nailing through the
4Complete the gas line installation.
5Complete the electrical
6Complete the vent installation.
7Install the hearth (if applicable).
8Install the facing.
9Install the mantel (if applicable).