PLACE THE BOILER
2. PLACE THE BOILER
A.PACKAGED BOILER
1.Remove crate top and sides. Remove any loose cartons. Remove burner support pedestal and nipple, if supplied
2.Lift boiler off crate pallet. Move to location determined in Chapter 1: Preinstallation.
3.Remove lifting frame and hardware.
4.
5.Proceed to Chapter 3: Piping the Boiler.
B.ASSEMBLED BLOCK BOILER
1.Move block to location determined in Chapter 1: Preinstallation.
2.Remove lifting frame and hardware.
3.Proceed to Section D: Install Coils or Plates
C.KNOCKDOWN BOILER
1.Place channel rails as shown in Figure 1.4.
2.Open the Section Assembly Kit cartons. These cartons contain the parts needed for assembly of the sections.
3.Place the Back Section on the floor as shown in Figure 2.1.
4.The Back Section combustion chamber area is lined with a ceramic fiber blanket liner. Make sure the liner is in good condition. Minor tears are not a problem, but there should be no holes in the insulation.
Figure 2.1: Lay Sections on Floor and Apply Rope Seal and Gaskets
10