PB Heat Gas/Oil Boilers manual Pipe Tankless Heaters if Used, Connect Supply Wiring

Page 36

INSTALL CONTROLS AND TRIM

3.Mount the High Limit Control bulb well in the left side 3/4" tapping of the coil cover plate if a tankless heater is not mounted in the upper right opening (Position 2). If a coil is installed there, mount the well in the 3/4" tapping to the left of the opening. See Figure 8.2.

CAUTION

Make sure that the gas ignition system components, electrical controls, junction boxes and electrical panels are protected from water (dripping, spraying, rain, etc.) during boiler operation and service (circulator or pump servicing, control replacements or other).

E.PIPE TANKLESS HEATERS IF USED

1.Connect piping to any installed tankless heaters. See Figure 8.3 for suggested piping for single coils and Figure 8.4 for suggested piping for dual coils.

F.CONNECT SUPPLY WIRING

1.Install all wiring in accordance with local codes, the National Electrical Code and other controlling agencies or governing bodies.

2.Use #14 gauge or heavier wire for supply wiring. Protect the circuit with a fused disconnect switch (by others).

CAUTION

The boiler/burner must be electrically grounded in accordance with the requirements of the authority having jurisdiction, or in the absence of such requirements, with the current edition of the National Electrical Code, ANSI/NFPA Number 70.

3.Follow the instructions in the Burner Manual and the Wiring Diagrams supplied with the burner and the boiler.

G.INSTALL CONTROL WIRING

1.Wire the boiler according to the wiring diagrams supplied with the burner and the boiler (in the Boiler Envelope).

2.Low Energy Safety Control wiring, if used, must follow the contour of the boiler. Some local codes may require that all wiring, even low voltage, be routed in conduit.

3.Install line voltage wiring in conduit.

4.Do not install single pole switches, including safety controls, in a grounded line.

34

Image 36
Contents Series LC/LCE Table of Contents Using this Manual Special Attention BoxesPreinstallation Accessibility ClearancesClearance from Combustible Construction Combustion and Ventilation AIRChimney or Vent Boiler Setting Foundation LayoutInstallation Survey Planning the LayoutVerify Components Foundation Lengths2A Series LC Shipping List Lwco2B Series LCE Shipping List Interm BackStandard and Optional Sections for Knockdown Boilers Standard and Optional Jacket Cartons, Front/Back PanelsStandard and Optional Jacket Cartons, Top/Side Panels 6A Burner Mounting Plates6B Burner Mounting Plates Trim CartonsControl Cartons Place the Boiler Packaged BoilerAssembled Block Boiler Knockdown BoilerApply Silcone Sealant Place the Boiler Series LC Boiler Assembly Right Side View Series LCE Boiler Assembly Right Side View Torque Specification/Procedure ModelLC/LCE Boiler Section Assembly Sequence Install Coils or Plates Hydrostatic Test the BoilerTankless Coil Ratings Apply Cleanout Cover Plates Install Flue CollarInstall Flue Baffles Install Chamber LinerLOW System Temperature Low Return Temperature Piping, GeneralPipe the Boiler PreparationReturn Connections @ 20F Output RiseSize Header Constant Low Temperature Variable Low TemperatureMultiple Boiler Installations Chilled Water SystemsHigh Flow Rate Piping Piping for Variable Low Temperature Systems, Single Boiler Pipe the Boiler Pipe the Boiler Assemble the Jacket Jacket Assembly Install the Burner Install Burner Mounting PlateVenting Burner ApplicationBeckett Carlin Gordon Power Webster Inches Piatt Chamber Burner Front Plate Extension Past Jacket InchesInstall Fuel OIL Piping Install GAS Supply PipingConnect Fuel Piping GeneralPipe Length PipeSpecific Gravity Multiply Capacity by Install Controls and Trim Install Safety Relief ValveInstall Drain Valve Install LOW Water CutoffsConnect Supply Wiring Install Control WiringPipe Tankless Heaters if Used Control and Pipe Tapping Locations Suggested Piping Single Tankless Coil Installation Starting the Boiler Check the PipingFill the Boiler RUN Burner CHECK-OUTCheck Boiler Controls Typical Combustion Chamber Pressure and Boiler Draft LossModel Combustion Chamber Pressure Boiler Draft Loss Maintenance Maintenance Annual Placing Boiler in OperationTo Shut Down the Boiler Monthly Maintenance Daily MaintenanceBoiler Ratings & Dimensions Series LC/LCE Boiler RatingsSeries LC Dimensional Diagram Series LC/LCE Boiler Dimensions Series LC/LCE Boiler DimensionsRepair Parts Series LC Boiler Assembly1A Series LC Repair Parts Description Part Selection Information Stock Code1B Series LC Repair Parts Series LCE Boiler Assembly 2A Series LCE Repair Parts 2B Series LCE Repair Parts Page Page Series LC/LCE