Burnham K50 manual Installation of BUILT-IN Heater, Testing Boiler Assembly for Leaks

Page 12

Fig. 8

INSTALLATION OF BUILT-IN HEATER

Open Tankless Heater Carton(s) If Supplied. Open Heater Opening Cover Plate Carton(s).

9.INSTALL BUILT-IN WATER HEATER(S) OR HEATER OPENING COVER PLATE(S), See Fig.

8. Heater may be installed in either End Section or, in some cases, in both End Sections. Heater Opening Cover Plates are used to cover any unused heater openings.

a.Place rubber gasket against surface of plate and align holes.

b.Place washer on each of 3/8” Cap Screws furnished and insert cap screws through plate and gasket.

Start all screws in taps before final tightening.

10.HYDROSTATIC TEST - After the boiler sections have been assembled, it is essential that the boiler be hydrostatically tested before the canopy, flue cover plates, jacket, or piping is installed.

a.Plug all boiler tappings and fill boiler completely with cold water.

CAUTION

DO NOT install gauge until after hydrostatic testing the boiler. Gauge failure may result.

b.All completed boilers must satisfactorily pass the prescribed hydrostatic test.

(1)STEAM BOILERS: The assembled boiler must be subjected to a hydrostatic test of 45 psig to 55 psig.

(2)HOT WATER BOILERS: The assembled boiler must be subjected to a hydrostatic test of 75 psig to 85 psig.

WARNING

Failure to properly hydrotest all boilers at the correct pressure may result in section assembly failure in operation.

12

Fig. 9

TESTING BOILER ASSEMBLY FOR LEAKS

11.EXAMINE BOILER CAREFULLY, INSIDE AND OUTSIDE, to insure against leaks from cocked nipples or through concealed breakage caused in shipping and handling. This precaution is for your protection and will simplify handling of necessary replacements and adjustment claims. After making certain that there are no leaks, drain boiler and remove plugs for boiler trim and other connections.

Open Boiler Sealing Carton.

12SEAL BETWEEN BOILER SECTIONS AND BASE, see Fig. 10.

a.Push ¾” braided ceramic fibre Rope (furnished) into gap between bottom of End Section and Low Base End Panel until rope touches Front and Rear Base

Frames. Place the 1-1/2” x 2” x 5/8” steel spacers between low base panel and section and in front of rope – align holes. Secure section to low base end panel with 3/8”-16 x 2” Cap Screws, washers and nuts.

b.Secure opposite end section to high base end panel with 3/8”-16 x 2” Cap Screws, washers and nuts.

c.Apply Furnace Cement to gaps between section assembly and base to make gas tight seal.

d.Check all joints between Boiler sections and use remaining Furnace Cement or Sealer Compound to make joints gas tight.

13.INSTALL FLUE COVER PLATES over cleanout openings on Front and Rear of Boiler. Use ¼” Carriage

Bolts installed at top and bottom of flue openings and secure with washer and jam nut to provide a fixed stud. Install flue cover plates over studs with insulation against Boiler and secure with washers and nuts, see Fig. 11.

14.CONNECT SUPPLY AND RETURN PIPING TO HEATING SYSTEM.

CLEARANCES – Steam and Hot water pipes shall have clearances of at least ½” from all combustible construction.

Image 12
Contents Series 5B Section I Equipment Check List Important Information Canadian Equipment Check List Canadian Equipment Check List Dimensional Data Natural GAS Maximum 14 W.C. Minimum 5.5 W.CDo not Install this Boiler on Carpeting Provide Combustion and Ventilation AIRBASE-BURNER-MANIFOLD Assemblys Single Manifold Base 5006B Thru 5014B Section BoilersLEH Section on Base Assembly of Center Sections Dual Manifold Bases 5015B Thru 5026B Section BoilersArrangement of Sections and Canopys Open Steam or Water Trim Carton Purpose of Tappings and Their LocationsInstallation of BUILT-IN Heater Testing Boiler Assembly for LeaksConnect Supply and Return Piping to Heating System Sealing of BASE, Installation Flue Covers and Canopies Attachment of Flue CoversOxygen Corrosion Page Page Page Page Recommended Water Boiler Piping Supply Connection & I Return ConnectionSupply Connections & 2 Return Connections Sizes 5006B Thru 5019BInstallation of Jacket Parts Common to ALL Boiler Sizes Installation of Jacket Support Brackets to Base END PanelsPage Exploded View of Jacket 6 Thru 10 Section Boilers Securing of CANOPY/DRAFTHOOD CANOPY/DRAFTHOOD Mounting Diagram Exploded View of Jacket 11 Thru 19 SECT. Boilers Completion of Jacket Installation 11 Thru 26 Section Boilers Exploded View of Jacket 20 Thru 22 SECT. Boilers Exploded View of Jacket 26 SECT. Boilers Shutoff Valve Between Safety Valve Steam Trim and ControlsMounting Elevations of M&M 150 and a 67M Float Lwco Water Trim and Controls Recommended Piping to BUILT-IN Tankless Heaters Open GAS Train CartonsOpen Gas Controls Cartons Installation of S8610M Module Pilot Piping EI Control System Robertshaw7000 A B Thru 5009BPilot Piping EI Control System V88A A B Thru 5026B NAT. GAS Canada 5006B Thru 5026B NAT. GASInstallation of Pilot Safety Switch Installation of Pilot Safety Switch EO Control SystemPilot Piping EO Control System Installation of EO and EE Mounting Bracket and Controls EE Control SystemSect. and larger boilers Pilot Piping EE Control SystemInstallation of Pilot Safety Switch EOP Control System Pilot Piping EOP Control SystemEEP Control System Pilot Piping EEP Control SystemPage Venting Single Vent System Manifold Vent SystemPage Section IV Operation GeneralTable IV Water Content Condensation Control VariationsBe sure power is off when checking high voltage connections A B Thru 5009B Schematic Wiring Diagram EI Control System V88 GAS Train Sequence of OperationA B Thru 5014B Canada 5006B Thru 5014BSchematic wiring diagram 15 Thru 26 SECT. Boilers EI Control SystemSequence of Operation Page Safety Switch Circuit Pilot FailureWiring diagram 6 Thru 14 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring diagram 15 Thru 26 SECT. Boilers Operating and safety controls. Should any EE Control System Wiring diagram 15 Thru 26 SECT. Boilers Proceed to Paragraph 15- Minimum Input Wiring Diagram 6 Thru 14 SECT. Boilers EOP Control System Turn on Main Power Switch. Main Power Light will light Wiring Diagram 15 Thru 26 SECT. Boilers EOP Control System Safety Switch Circuit Wiring Diagram 6 Thru 14 SECT. Boilers EEP Control System Pilot Failure Safety Switch Circuit Wiring Diagram 15 Thru 26 SECT. Boilers EEP Control System Make sure all manual resets are activated where applicable Normal Operation Sequence Page Check GAS Input Rate to Boiler Minimum Input Adjustments V8944B Combination ValveMotorized Modulating Actuator ScrewTest Ignition System Safety SHUT-OFF Device AS Follows Thermocouple Pilot System Combustion Chamber BURN-OFFSection V Service Removal of Jacket Front PanelAvoid Breathing Fiber Particulates and Dust Cleaning of Flueways LubricationPilot Locations Main Burner Flame Adjustment Pilot Flame Honeywell Q3481BPilot Flame Honeywell Q179D Pilot w/THERMOCOUPLEPilot Flame Honeywell Q179C Pilot Honeywell Q327A Pilot w/THERMOCOUPLEDo not drain water below gauge glass Base Parts JacketsSeries 5B Base Parts 5006B thru 5014B Number in in Table Relates to Corresponding NumberBase Parts Series 5B Base Parts 5015B thru 5026B 5015B 5016B 5017B 5018B 5019B 5020B 5021B 5022B 5024B 5026BBase Parts Canopy Boiler Size Quantity Part SizeIntegral Canopy Drafthoods & Sections Series 5B Section Replacement Chart Series 5B Base / Pilot Assemblies Series 5B Jackets 60413075 5007B Lower Top Panel 2 x 37-3/16 60413085 5008B 2 x 20-7/8 Complete Jackets Jackets Boiler Size Boiler Size 5006B 5008B 5009B 5014B 5015B 5016B 5017B 5026BV88A GAS Trains Canada Natural GAS only Fluid Power GAS Trains USA 100 5006B 5009B 5015B 5016B 5017B101 Diaphragm Valve LO-HI-LO GAS Train Canada Natural GAS onlyFluid Power GAS Trains Canada 102103 Ignition Module & Support Bracket EI Control SystemPilot Safety Switch 104Description Manifold Module Support L62GB-3C 105 A. 5010B-5026B NAT. GAS Canada 5006B-5026B NAT. GAS106 Transformer & Pilot Line Regulator EO Control System107 108 109 110 111 EOP & EEP Control PanelEI Control System Pilot Assembly 112113 6236007 NAT. GASEI GAS 114 6236003 NAT. GASNot Available for LP Date Service Performed 115Limited Warranty 116